Home / Counties / Williamson

Data centers in Williamson County, Texas

7 projects and 26 dated records · newest item checked 2026-11-18; older items keep their own dates

In short: Williamson County, Texas has 7 tracked data center or related power projects: Taylor Technology Campus (formerly Project Mustang) (status: Approved (development agreement)); Skybox Hutto campus (Hutto 1–4) (status: Registered (TDLR)); Colovore Hutto data center (status: Registered (TDLR)); Sabey Austin Building B data halls (Round Rock) (status: Existing campus; new data halls registered (TDLR)); and 3 more, and 26 dated public records. Most recent record (Nov 17, 2026): CBS Austin: Georgetown P&Z unanimously recommended denying the Inner Loop Exchange rezoning; council expected Dec 8 and needs a 6-1 vote to approve.

Free · every Friday

Get updates for your county

New filings, votes and hearings in Williamson County, in one email every Friday, free for your first month. Free accounts cover 1 county. Want it same-day? Neighbor, $4/mo, first 30 days free.

Sample

New city council record · Williamson County

Record date 2026-10-08 · Official record

Agenda item 6: council to consider development agreement for 664.39-acre Taylor Technology Campus (formerly Project Mustang); agenda posted Oct 2.

Project: Taylor Technology Campus (formerly Project Mustang)

Read the public source: taylortx.api.civicclerk.com ↗

Sample of the alert format, using a real public record. The record date is not in the future. Last checked 2026-10-06.

Map of Williamson County projects

Data centerPower / generationPower plant permitChip plantLead (unconfirmed)Approximate location (town or county center)

Pins with a dashed outline are approximate: the source names only a town or the county, so the pin sits at the town or county center, not the site. Open the statewide map.

Projects

Williamson County · Taylor (just east of city limits, between FM 112 and US 79)

Taylor Technology Campus (formerly Project Mustang)

Big Watt Digital; PowerHouse Data Centers

Approved (development agreement)

Size: 664 acres; data center facilities plus on-site power generation (City of Taylor); up to 1 GW data center capacity via dedicated behind-the-meter power from a new 750 MW natural gas plant; first power targeted 1H 2028, first phase aiming for 500 MW (DCD, Oct 15 2026, attributing company plans)

Last verified 2026-10-15 · 8 sources

Williamson County · Hutto (4200 and 3399 County Road 132)

Skybox Hutto campus (Hutto 1–4)

Skybox (named in TDLR project titles); Prologis (per Hoodline, which calls Hutto Data Center Campus LLC a Prologis affiliate); owners Hutto Data Center Campus, LLC (Hutto 1, 2, 4) and Hutto Data Center 3, LLC (Hutto 3) (TDLR)

Registered (TDLR)

Size: Sizes as each TDLR filing states them: Hutto 1 core/shell, square footage field 253,730 sq ft while its scope text says 235,730 sf; Hutto 1 initial improvements 235,730; Hutto 1 fit-out 235,730; Hutto 2 core/shell 235,730; Hutto 2 fit-out 234,820; Hutto 2 fit-up 234,820; Hutto 3 core/shell 492,350; Hutto 4 core/shell 846,300 (about 844,300 sq ft data center plus about 20,000 sq ft office per its scope text); core/shell filings list future data center use (TDLR). The figures differ between filings and are shown as filed. Hoodline reports a planned 600 MW of IT across 3.88M sq ft (citing DCD)

Investment: TDLR est. costs: Hutto 1 core/shell $86M, initial improvements $149M, fit-out $163M; Hutto 2 core/shell $78.3M, fit-out $125M, fit-up $470M; Hutto 3 core/shell $283,046,463; Hutto 4 core/shell $550M. Hoodline cites The Real Deal (Jul 2023) for $5–10B across up to six buildings

Last verified 2026-10-12 · 12 sources

Williamson County · Hutto (2401 Innovation Boulevard, per TDLR)

Colovore Hutto data center

Colovore (TDLR owner Colovore Austin 1, LLC)

Registered (TDLR)

Size: One-story 192,694 sq ft data center building with admin area and screened equipment yard (TDLR)

Investment: Est. $280M (TDLR, as filed)

Last verified 2026-10-18 · 1 sources

Williamson County · Round Rock (1300 Louis Henna Blvd., per TDLR)

Sabey Austin Building B data halls (Round Rock)

Sabey Data Centers (TDLR owner)

Existing campus; new data halls registered (TDLR)

Size: Data Halls B35 and B36, ~77,000 sq ft each (TDLR)

Investment: Est. $40M per data hall (TDLR, as filed)

Last verified 2026-10-18 · 2 sources

Williamson County · Taylor (southeast side, inside Carlos G Parker Blvd between Martin Luther King Blvd and the railroad tracks)

Blueprint Projects Data Center (BPP Projects LLC, southeast Taylor)

BPP Projects LLC / Blueprint Data Centers; site bought by NCP Travis TPP Project LLC, the project's investor (Taylor Press)

Approved (Chapter 380 agreement; Employment Center plan)

Size: 135,000 sq ft, three buildings, electricity substation, backup generators, closed-loop cooling (City of Taylor); 60 MW gross utility capacity, energization 2026 and 2027 (company website)

Investment: $1 billion total over three phases (City of Taylor); minimum capital investment of $225,000,000 under the agreement (Taylor EDC)

Last verified 2026-11-01 · 4 sources

Williamson County · Taylor (1051 County Road 401, northeast of the Samsung site, per City of Taylor)

KDC Project Comal (1051 County Road 401, Taylor)

KDC Real Estate Development and Investments

Approved (annexation and Employment Center zoning)

Size: About 210 acres for the data center plus ~10 acres of retail/office (City of Taylor; Taylor Press); DCD says 220 acres, six data center buildings and two substations, 360 MW (DCD)

Investment: $2.5 billion (Taylor EDC CEO, per Taylor Press)

Last verified 2026-11-02 · 4 sources

Williamson County · Georgetown (NE Inner Loop at E University Ave)

Inner Loop Exchange PUD data center (Georgetown, 2026-6-PUD)

Oakwell Capital (property owner, per city staff report); Kimley-Horn (applicant/agent, per staff report)

Proposed / in development

Size: About 28.031 acres; PUD would raise the maximum data center building size from 5,000 sq ft (C-2) to 290,000 sq ft (city staff report). 68 MW per developer flyers (KVUE) and resident comments in the packet; MW not stated by the city; Texas Construction Hub (Nov 13 2026) also reports 68 MW

Investment: $1B (reported by Texas Construction Hub, Nov 13 2026; not stated in city records)

Last verified 2026-11-18 · 4 sources

Power plants (2)

New and proposed power plants in Williamson County from TCEQ air permits and ERCOT grid records, including plants built to serve data centers. Permitted or proposed is not built. An air permit lets a company build; it does not mean a plant exists or will be built.

Near Taylor

Big Watt Digital power units (Taylor)

Air permit pending Data center tie

Applicant
Big Watt Digital LLC
Permit
Standard permit for electric generating units: 185729
Filed with TCEQ
Oct 14, 2026
Size
449 MW (ERCOT GIS report (Oct 2026), 27INR0606, projected Dec 2028)
Who it serves
Data center: Tracked Taylor Technology Campus (Big Watt Digital).
Linked projects
Taylor Technology Campus (formerly Project Mustang)

Official record TCEQ air permit project 416657 ↗ · Official record ERCOT GIS report (Oct 2026), 27INR0606, projected Dec 2028 ↗

Checked Nov 25, 2026. Permitted or proposed is not built.

Near Taylor

Compal USA Technology power units (Taylor)

Air permit issued Undisclosed tie

Applicant
Compal USA Technology Inc
Permit
Standard permit for electric generating units: 185221
Filed with TCEQ
Sep 1, 2026
Permit issued
Nov 18, 2026
Size
Not stated in the permit record
Who it serves
Undisclosed: Applicant Compal USA Technology Inc, 1069 FM 3349, Taylor; EGU standard permit 185221 received Sep 1, issued Nov 18, 2026; the record does not state what the units serve; size not stated; no ERCOT GIS (Oct 2026) match.

Official record TCEQ air permit project 414297 ↗

Checked Nov 25, 2026. Permitted or proposed is not built.

All Texas power plants we track →

Chip plants (1)

Semiconductor fabs and wafer plants in Williamson County from TCEQ air permits, state tax-break filings (JETI and Chapter 313) and CHIPS Act records. These are counted separately from data centers. Proposed, permitted or incentive-approved is not built. A tax-break application or air permit does not mean a plant exists or will be built.

Taylor

Samsung Austin Semiconductor, Taylor site

Air permits issued Jul 7, 2025 (incl. PSD and GHG PSD); CHIPS award final Chip plant

Company
Samsung Austin Semiconductor, LLC
What it is
Leading-edge logic fabs and an R&D fab (per the CHIPS award)
Site
1530 FM 973, Taylor
Air permits
167820, GHGPSDTX245, PSDTX1654
State tax records
10 Chapter 313 agreements
Investment
Over $37 billion in Central Texas (CHIPS award page, Taylor and Austin combined)
Note
TCEQ permits 167820, PSDTX1654 and GHGPSDTX245. The CHIPS page says all funded facilities are expected to be operational by 2030 (projection).

Official record TCEQ air permit project 381733 (SEMICONDUCTOR MANUFACTURING FACILITY; status complete) ↗ · Official record Comptroller Chapter 313 agreement 1620: Taylor ISD agreement (2021) ↗ · Official record Comptroller Chapter 313 agreement 2052: Taylor ISD, Fab 2 ↗ · Official record Comptroller Chapter 313 agreement 2053: Taylor ISD, Fab 3 ↗ · Official record Comptroller Chapter 313 agreement 2054: Taylor ISD, Fab 4 ↗ · Official record Comptroller Chapter 313 agreement 2055: Taylor ISD, Fab 5 ↗ · Official record Comptroller Chapter 313 agreement 2056: Taylor ISD, Fab 6 ↗ · Official record Comptroller Chapter 313 agreement 2057: Taylor ISD, Fab 7 ↗ · 4 more records

Checked Nov 25, 2026. Proposed or permitted is not built.

All Texas chip plants we track →

Records & actions

2026-11-17
City council News report · Inner Loop Exchange PUD data center (Georgetown, 2026-6-PUD)

CBS Austin: Georgetown P&Z unanimously recommended denying the Inner Loop Exchange rezoning; council expected Dec 8 and needs a 6-1 vote to approve.

Source: cbsaustin.com ↗
2026-11-17
City council News report · Inner Loop Exchange PUD data center (Georgetown, 2026-6-PUD)

Georgetown P&Z Nov 17, 6 p.m.: public hearing on 2026-6-PUD Inner Loop Exchange, rezoning ~28 acres at NE Inner Loop/E University Ave to a PUD allowing a data center up to 290,000 sq ft; staff report lists 32 written comments opposed.

Source: d3n9y02raazwpg.cloudfront.net ↗
2026-11-13
News News report · Inner Loop Exchange PUD data center (Georgetown, 2026-6-PUD)

Texas Construction Hub: Inner Loop Exchange is a proposed $1B, 68 MW data center up to 290,000 sq ft on ~28 acres; P&Z hearing Nov 17.

Source: texasconstructionhub.com ↗
2026-11-03
City council News report

Hutto notice: P&Z hearing Nov 3, 7 p.m., on replat of Hutto Data Center Campus Subdivision One (97.866 acres, six lots, north/east of CR 132).

Source: tx-hutto2.civicplus.com ↗
2026-10-26
News News report · Taylor Technology Campus (formerly Project Mustang)

CBS Austin: TCEQ says it received Big Watt Digital's air permit application for on-site gas generators; technical review not begun.

Source: cbsaustin.com ↗
2026-10-22
City council News report

Taylor Press: Taylor council held first-reading hearing Oct 22 on code amendments with digital infrastructure (data center) rules; no action taken.

Source: taylorpress.net ↗
2026-10-15
News News report · Taylor Technology Campus (formerly Project Mustang)

DCD: PowerHouse and Big Watt secured Taylor City Council approval for up to 1 GW campus with 750 MW on-site gas; first power targeted 1H 2028 (company plans via DCD).

Source: datacenterdynamics.com ↗
2026-10-09
News News report · Taylor Technology Campus (formerly Project Mustang)

KUT: council unanimously approved agreement with Big Watt/PowerHouse covering water, noise and air-quality conditions for the 664-acre campus.

Source: kut.org ↗
2026-10-08
City council Official record · Taylor Technology Campus (formerly Project Mustang)

Agenda item 6: council to consider development agreement for 664.39-acre Taylor Technology Campus (formerly Project Mustang); agenda posted Oct 2.

Source: taylortx.api.civicclerk.com ↗
2026-10-08
City council News report · Taylor Technology Campus (formerly Project Mustang)

CBS Austin: Taylor City Council approves Taylor Technology Campus development agreement 5-0 ("unanimously"); formal annexation is a later step under the agreement.

Source: cbsaustin.com ↗
2026-10-08
City council News report · Taylor Technology Campus (formerly Project Mustang)

Taylor Press: council unanimously approved the development agreement after public comment; no tax incentives; annexation expected later.

Source: taylorpress.net ↗
2026-10-02
City council Official record · Taylor Technology Campus (formerly Project Mustang)

City of Taylor publishes proposed development agreement for 664-acre Taylor Technology Campus; council to vote on the agreement Oct 8; no tax abatements requested.

Source: taylortx.gov ↗
2026-10-02
News News report · Taylor Technology Campus (formerly Project Mustang)

KUT: Taylor council to vote Oct 8 on deal to annex Big Watt/PowerHouse data center site and set conditions.

Source: kut.org ↗
2026-10-01
City council News report · Skybox Hutto campus (Hutto 1–4)

Taylor Press: Hutto council approves 6-0 rezoning of ~140-acre Megasite parcel for Skybox data center and power station PUD, with cooling and sales-tax conditions.

Source: taylorpress.net ↗
2026-10-01
City council News report · Skybox Hutto campus (Hutto 1–4)

OpenTexas civic record page: Skybox Data Center (Project SQL) rezoning approved 6-0 by Hutto City Council.

Source: hutto.myopentexas.org ↗
2026-09-30
Building registration (TDLR) Official record · Skybox Hutto campus (Hutto 1–4)

TDLR TABS: 'Skybox Hutto 4 – Core/Shell', 846,300 sq ft, est. $550M, future data center use; owner Hutto Data Center Campus, LLC.

Source: tdlr.texas.gov ↗
2026-09-17
State action News report · Blueprint Projects Data Center (BPP Projects LLC, southeast Taylor)

Taylor Press: AG Paxton is investigating whether the former parkland site in southeast Taylor can legally host the Blueprint Projects data center.

Source: taylorpress.net ↗
2026-09-02
Building registration (TDLR) Official record · Colovore Hutto data center

TDLR TABS: 'Colovore Hutto', one-story 192,694 sq ft data center, est. $280M, 2401 Innovation Blvd, Hutto; owner Colovore Austin 1, LLC.

Source: tdlr.texas.gov ↗
2026-03-27
News News report · KDC Project Comal (1051 County Road 401, Taylor)

Taylor Press: $2.5B Project Comal approved with closed-loop cooling, 30M-gallon fill cap, 300-ft buffer, 70 dB night limit.

Source: taylorpress.net ↗
2026-03-26
City council Official record · KDC Project Comal (1051 County Road 401, Taylor)

Taylor council unanimously approved annexation and Employment Center zoning for KDC Project Comal, a 360 MW, six-building campus (DCD; City of Taylor).

Source: taylortx.gov ↗
2025-10-10
Building registration (TDLR) Official record · Sabey Austin Building B data halls (Round Rock)

TDLR TABS: 'Sabey Austin Building B' Data Halls B35 and B36, ~77,000 sq ft and est. $40M each, 1300 Louis Henna Blvd, Round Rock.

Source: tdlr.texas.gov ↗
2025-09-19
Building registration (TDLR) Official record · Skybox Hutto campus (Hutto 1–4)

TDLR TABS: 'Skybox - Hutto 2 Fit Up', interior improvements to Building 2, est. $470M; owner Hutto Data Center Campus, LLC.

Source: tdlr.texas.gov ↗
2024-08-08
Tax abatement Official record · Blueprint Projects Data Center (BPP Projects LLC, southeast Taylor)

Taylor City Council unanimously authorized a Chapter 380 economic development agreement with BPP Projects LLC for the Blueprint Projects data center (city page).

Source: taylortx.gov ↗
2024-05-10
Building registration (TDLR) Official record · Skybox Hutto campus (Hutto 1–4)

TDLR TABS: 'Skybox - Hutto 3 Core Shell', 492,350 sq ft, est. $283M, 3399 CR 132; owner Hutto Data Center 3, LLC.

Source: tdlr.texas.gov ↗
2024-04-03
Building registration (TDLR) Official record · Skybox Hutto campus (Hutto 1–4)

TDLR TABS: 'Skybox - Hutto 2 Core/Shell', 235,730 sq ft, est. $78.3M, future data center use; owner Hutto Data Center Campus, LLC.

Source: tdlr.texas.gov ↗
2023-10-19
Building registration (TDLR) Official record · Skybox Hutto campus (Hutto 1–4)

TDLR TABS: 'Skybox - Hutto 1', core/shell building for future data center use, 4200 CR 132, est. $86M; owner Hutto Data Center Campus, LLC.

Source: tdlr.texas.gov ↗

Long-form guide: Data centers in Williamson County, Texas.

Sources we check and archive

What we use to confirm information, and what is kept for members to research and search. The newest tracker-record check is 2026-11-25; that is not a date when every record was rechecked. Each record keeps its own date. 302 distinct source sites are cited. Official records come first. How we verify →

Williamson County: 7 projects, 26 dated records, 15 archived news articles (members archive).

Checked to confirm information

  • County commissioners court agendas and minutes 87 records
  • City council and planning & zoning agendas and minutes 89 records
  • Tax abatement agreements and filings 29 records
  • TDLR building registrations (TABS) 140 records
  • TCEQ air and water permits and notices 32 records
  • ERCOT and PUC filings, large-load queue and dockets 41 records
  • State agency and Governor's office actions 39 records
  • Federal filings (SEC and others) 13 records
  • Court filings and lawsuits 6 records
  • Company announcements (attributed as claims) 45 records
  • Comptroller data center tax-exemption registry 192 entries
  • Water Data for Texas (TWDB) reservoir levels and ERCOT demand 118 lakes
  • Local and national news outlets (context, attributed) 343 outlets

Spot an error or a missing filing? Email [email protected] with the source link.