Texas Data Center Lead Intel: sample weekly report

This is what a Lead Intel subscriber gets each week: new Texas data center filings, approvals and hearings, with the developer, stage, size and dates as stated in public records, and why each one matters for vendors, contractors and brokers. This sample uses real records from our tracker (filings dated Sep 30 to Oct 15, 2026; checked Oct 16, 2026). Every fact links to its source and is labeled Official record, Company claim or News report.

Start Lead Intel · $179/mo Annual · $1,490/yr Book a call

This week's policy watch

  • ERCOT reports about 474 GW of large loads seeking interconnection as of June 2026, about 90% of them data centers. Official record ercot.com ↗
  • On Sep 21 2026 the Governor directed TCEQ to halt all permits sought by data centers until ERCOT completes its audit. TCEQ's compliance update is due to the Governor on Oct 19 2026. Official record gov.texas.gov ↗
  • ERCOT plans to file its Batch Zero eligibility and community-impact reports with the PUC by Dec 10 2026, and has paused energizing new large-load data centers until the verification and audit are complete (ERCOT, Sep 11). Official record ercot.com ↗

What this means for sellers: state permits for data centers are on hold and ERCOT has paused energizing new large loads, so near-term work tilts toward projects that already have building registrations, local approvals or on-site power. Watch the Oct 19 and Dec 10 dates.

New and active leads (7)

Lead 1 · Williamson County · Taylor (just east of city limits, between FM 112 and US 79)

Taylor Technology Campus (formerly Project Mustang)

Developer (as stated in records)
Big Watt Digital; PowerHouse Data Centers
Stage
Approved (development agreement)
Size / power
664 acres; data center facilities plus on-site power generation (City of Taylor); up to 1 GW data center capacity via dedicated behind-the-meter power from a new 750 MW natural gas plant; first power targeted 1H 2028, first phase aiming for 500 MW (DCD, Oct 15 2026, attributing company plans)

Latest milestones

  • Oct 8 2026: Taylor City Council approved the development agreement for the 664-acre campus 5-0. Annexation is a later step. News report cbsaustin.com ↗
  • Agreement terms published by the City: closed-loop cooling using reclaimed water, noise cap, 300–700 ft setbacks. Official record taylortx.gov ↗
  • Developers Big Watt Digital and PowerHouse Data Centers plan up to 1 GW with a new 750 MW natural gas plant; first power targeted 1H 2028, first phase aiming for 500 MW (company plans, reported by DCD). News report datacenterdynamics.com ↗

Why it matters for vendors, contractors and brokers: Up to 1 GW of planned capacity plus a 750 MW on-site gas plant (company plans) means gas turbine, switchgear, transformer, closed-loop cooling and civil packages. The agreement sets a preliminary plat deadline of Apr 8 2027, so design and site-work bids come first.

Lead 2 · Willacy County · Santa Monica area (1392 FM 1420)

Project Kati 2 (MFE-A-Kati2 Building 1)

Developer (as stated in records)
Soluna (TDLR owner Soluna KK Energy Service Co LLC); Metrobloks (co-development partner per Soluna release)
Stage
Registered (TDLR)
Size / power
TDLR: single-story AI data center, about 471,884 sq ft, ±112 MW critical IT load (TDLR scope). Soluna (Jan 15 2026, company): initial 100+ MW Critical IT phase of a larger campus with roadmap supporting more than 300 MW total CIT
Investment
Est. $471.8M (TDLR)

Latest milestones

  • Oct 7 2026: TDLR registration for Kati II Building 1 at 1392 FM 1420: 471,884 sq ft, ±112 MW critical IT, est. $471.8M; owner Soluna KK Energy Service Co LLC; start Oct 8 2026, completion Oct 8 2027. Official record tdlr.texas.gov ↗
  • Soluna says the first 100+ MW phase is part of a campus roadmap of more than 300 MW, co-developed with Metrobloks. Company claim solunacomputing.com ↗

Why it matters for vendors, contractors and brokers: A new state building registration with a stated start date (Oct 8 2026) and a ±112 MW IT load: an early signal for electrical, mechanical and building-envelope subcontractors in the Rio Grande Valley.

Lead 3 · Bastrop County · Cedar Creek (Earl Callahan Rd near Walter Hoffman Road)

Project Longhorn – Building One

Developer (as stated in records)
Owner Roger Donald Wallace (TDLR; tenant field 'Not Assigned'); BlackChamber developing the data center portion, Pacifico Energy the power facility (Community Impact, news); design firm Gensler (Dallas)
Stage
Registered (TDLR)
Size / power
498,165 sq ft (TDLR)
Investment
Est. $366M (TDLR)

Latest milestones

  • Oct 7 2026: TDLR registration for Project Longhorn – Building One, Earl Callahan Rd, Cedar Creek: 498,165 sq ft, est. $366M; start Nov 30 2026, completion Jan 31 2028; owner listed as Roger Donald Wallace; design firm Gensler. Official record tdlr.texas.gov ↗
  • Community Impact reports this is the first of two data center buildings planned by Pacifico Energy (power plant) and BlackChamber (data center). The TDLR record names neither company. News report communityimpact.com ↗

Why it matters for vendors, contractors and brokers: The TDLR filing names the design firm (Gensler, Dallas) and a Nov 30 2026 construction start: a window for pre-engineered metal building, site-work and MEP bidders. Community Impact reports a second building is planned.

Lead 4 · Dallas County · Lancaster

STACK DFW02 Lancaster data center campus (DFW02A, DFW02A-P2, DFW02B)

Developer (as stated in records)
STACK Infrastructure (per TDLR project names "STACK - DFW02A" and "STACK - DFW02A-P2", and STACK's DFW02 campus brochure, whose site plan labels a DFW02B building); owner entities SI DFW02A, LLC and SI DFW02CAMPUS LLC (TDLR)
Stage
Registered (TDLR)
Size / power
Three two-story office and data center buildings: DFW02A 360,028 sq ft; DFW02A-P2 360,044 sq ft; DFW02B 360,044 sq ft (TDLR). STACK's brochure describes a 193-acre DFW02 campus with 312 MW critical capacity expandable to 504 MW; its site plan shows DFW02A at 96MW and DFW02B, C, D and E at 54MW each (company)
Investment
TDLR estimated costs: DFW02A $79.7M; DFW02A-P2 $202.2M; DFW02B $540M

Latest milestones

  • Oct 5 2026: TDLR registration for DFW02B, 1130 E. Belt Line Rd, Lancaster: 360,044 sq ft two-story office and data center, est. $540M; owner SI DFW02CAMPUS LLC; start Mar 1 2027, completion Dec 14 2028. Official record tdlr.texas.gov ↗
  • STACK Infrastructure's DFW02 brochure describes a 193-acre campus with 312 MW critical capacity, expandable to 504 MW, and labels a 54 MW DFW02B building on its site plan. The DFW02B filing itself doesn't name STACK. Company claim stackinfra.com ↗

Why it matters for vendors, contractors and brokers: A third building on an existing DFW campus with an estimated $540M in work, a named architect (Corgan) and a Mar 2027 start: an expansion that local trade contractors and suppliers can plan for.

Lead 5 · Williamson County · Hutto (4200 and 3399 County Road 132)

Skybox Hutto campus (Hutto 1–4)

Developer (as stated in records)
Skybox (named in TDLR project titles); Prologis (per Hoodline, which calls Hutto Data Center Campus LLC a Prologis affiliate); owners Hutto Data Center Campus, LLC (Hutto 1, 2, 4) and Hutto Data Center 3, LLC (Hutto 3) (TDLR)
Stage
Registered (TDLR) + rezoning approved
Size / power
Sizes as each TDLR filing states them: Hutto 1 core/shell, square footage field 253,730 sq ft while its scope text says 235,730 sf; Hutto 1 initial improvements 235,730; Hutto 1 fit-out 235,730; Hutto 2 core/shell 235,730; Hutto 2 fit-out 234,820; Hutto 2 fit-up 234,820; Hutto 3 core/shell 492,350; Hutto 4 core/shell 846,300 (about 844,300 sq ft data center plus about 20,000 sq ft office per its scope text); core/shell filings list future data center use (TDLR). The figures differ between filings and are shown as filed. Hoodline reports a planned 600 MW of IT across 3.88M sq ft (citing DCD)
Investment
TDLR est. costs: Hutto 1 core/shell $86M, initial improvements $149M, fit-out $163M; Hutto 2 core/shell $78.3M, fit-out $125M, fit-up $470M; Hutto 3 core/shell $283,046,463; Hutto 4 core/shell $550M. Hoodline cites The Real Deal (Jul 2023) for $5–10B across up to six buildings

Latest milestones

  • Sep 30 2026: TDLR registration for Skybox Hutto 4 – Core/Shell, 846,300 sq ft, est. $550M, future data center use; owner Hutto Data Center Campus, LLC; start Jan 20 2027. Official record tdlr.texas.gov ↗
  • Oct 1 2026: Hutto City Council approved 6-0 a rezoning of about 140 acres in the Hutto Megasite for a data center and on-site power PUD. Official record hutto.myopentexas.org ↗
  • Conditions include closed-loop cooling and paying local sales taxes on construction and power generation; Skybox said securing ERCOT power may take about two more years. News report taylorpress.net ↗

Why it matters for vendors, contractors and brokers: Two signals in one week: a fourth core/shell registration ($550M) and a city rezoning for a further phase with on-site power. Long-cycle work for electrical, cooling and power-generation vendors in the Austin–Round Rock corridor.

Lead 6 · Hudspeth County · Desert Haven area

Hueco Ranch data center campus (Desert Haven)

Developer (as stated in records)
ServerDomes Global (named by Hudspeth County Judge); Kaufman & Company also named in some news accounts not opened here; CEO David J. Keegan (KFOX14)
Stage
Proposed / in development
Size / power
No official size. ServerDomes project page (re-opened Oct 13 2026; Wayback capture https://web.archive.org/web/20261013162209/https://serverdome-global.com/projects/modular-data-infrastructure): 350 MW planned, titled 'Hueco Ranch 24,000 Acres', page header reads 'Utah, USA' (company). CEO letter (Oct 10, via KFOX14): reports of a 24,000-acre development are incorrect; site is 2,000 acres, phase one 700 acres with 10 domes 500 ft wide and 65 ft high (company via news). The two company statements differ and are shown as stated
Investment
About $15B (project representatives, as relayed by Hudspeth County Judge MacKenzie, Oct 9 2026 official message)

Latest milestones

  • Oct 9 2026: Hudspeth County Judge confirmed a proposed ~$15B campus near Desert Haven linked to ServerDomes Global; no county abatement sought; road-use agreements being worked (figures from project representatives). Official record co.hudspeth.tx.us ↗
  • CEO letter (Oct 10): site is 2,000 acres, phase one 700 acres, behind-the-meter gas; company says it will attend the Oct 27 Commissioners Court. News report kfoxtv.com ↗
  • Company project page lists 350 MW planned, first 80 MW in 16 months. Company claim serverdome-global.com ↗

Why it matters for vendors, contractors and brokers: Early-stage and far West Texas, with behind-the-meter gas claimed. Watch the Oct 27 commissioners court appearance and road-use agreements for civil, road, gas and modular-building vendors. The company's own size figures conflict, so treat them with care.

Lead 7 · Briscoe County · ~5 mi south of Silverton along Hwy 207

Soluna Briscoe County Reinvestment Zone #6 (near Project Dorothy)

Developer (as stated in records)
Soluna Energy subsidiaries: Soluna Dorothy 3 Energy ServiceCo. LLC, Soluna DV BNSF Energy HoldCo. LLC (owners); STX-01 LLC (abatement applicant) (county notice); planned Soluna–Applied Digital joint venture for Dorothy 3 Phase 1 (company; Soluna 8-K)
Stage
Proposed / in development
Size / power
403.397 acres; one or more data centers (county notice)
Investment
Estimated value of improvements incl. business personal property more than $8B (county notice)

Latest milestones

  • County notice: Briscoe County Commissioners Court hearing Nov 9 2026, 9 a.m., Silverton, on Reinvestment Zone #6 (403.397 acres) and Soluna Chapter 312 abatement applications; estimated improvements more than $8B; applicant STX-01 LLC. Official record co.briscoe.tx.us ↗

Why it matters for vendors, contractors and brokers: A dated public hearing with a stated improvement value of more than $8B. Tax-abatement hearings come before construction, so this is an early look for site, power and construction firms.

Get this every week

Lead Intel ($179/mo or $1,490/yr): Early signals before projects are announced. 3 seats. Includes: Rezonings, abatement applications, generator and turbine air permits; Large-load and substation filings; Developer and EPC fields, weekly Texas lead report; CRM-ready exports and webhooks; Terrafab / SpaceX Tracker add-on included.

Start Lead Intel · $179/mo Annual · $1,490/yr Book a call

Need more than Lead Intel (API, bulk data or custom counties)? See Enterprise. Questions: [email protected].

Texas Data Center Watch is neutral: we report what public records, companies and news outlets say, and we don't endorse or oppose any project. Payment never buys coverage. See methodology and independence.