Home / Williamson County / Project
Taylor Technology Campus (formerly Project Mustang)
Big Watt Digital; PowerHouse Data Centers
In short: Location: Taylor (just east of city limits, between FM 112 and US 79), Williamson County, Texas. Status: Approved (development agreement). Developer or parties: Big Watt Digital; PowerHouse Data Centers. Size: 664 acres; data center facilities plus on-site power generation (City of Taylor); up to 1 GW data center capacity via dedicated behind-the-meter power from a new 750 MW natural… Latest record (Oct 26, 2026): CBS Austin: TCEQ says it received Big Watt Digital's air permit application for on-site gas generators; technical review not begun. Last verified Oct 15, 2026.
- Status
- Approved (development agreement)
- Developer / parties
- Big Watt Digital; PowerHouse Data Centers
- Location
- Taylor (just east of city limits, between FM 112 and US 79), Williamson County
- Size
- 664 acres; data center facilities plus on-site power generation (City of Taylor); up to 1 GW data center capacity via dedicated behind-the-meter power from a new 750 MW natural gas plant; first power targeted 1H 2028, first phase aiming for 500 MW (DCD, Oct 15 2026, attributing company plans)
- Reported benefits
- Developers commit $28.2M for community investments and nonprofit support; City projects $1.38B gross tax revenue over 20 years; developers are not asking for tax abatements (City of Taylor)
- Concerns / impacts
- Noise, water use, setbacks (City of Taylor); residents objected at the Oct 8 hearing (Taylor Press; KUT)
- Last verified
- 2026-10-15
Milestones
- Jan 8–Jul 23 2026 discussed in City Council executive sessions, no action taken
- Aug 3 2026 project made public by the City
- Aug 18 2026 Planning and Zoning Commission tabled it for 90 days pending more information and data center regulations
- Sep 3 2026 developers withdrew zoning and annexation application
- Oct 2 2026 City published a proposed development agreement (closed-loop cooling using reclaimed water, noise capped at the greater of 65 dBA or pre-development level, 300–700 ft setbacks, developers to withdraw their TCEQ wastewater discharge permit application) (City of Taylor)
- Oct 8 2026 City Council approved the development agreement unanimously (Taylor Press; KUT; Wilco Liberty Project, news)
- CBS Austin reports it passed 5-0 (news)
- official minutes not yet posted. The vote approved a 20-year development agreement (extendable 15 years)
- it did not annex the site. Under the agreement the developer must submit a complete preliminary plat by Apr 8 2027 and file a voluntary annexation petition within seven days after plat approval or conditional approval (Wilco Liberty Project, citing agreement/packet). Formal annexation remains a later City action. Site is currently in unincorporated Williamson County
Linked power & water
Power
- News report 750 MW behind-the-meter gas plant: Up to 1 GW of data center capacity via dedicated behind-the-meter power from a new 750 MW natural gas plant; first power targeted 1H 2028 (DCD, attributing company plans). datacenterdynamics.com ↗
- Official record ERCOT queue: Big Watt Mustang Power (27INR0606): ERCOT GIS report (Sept 2026) lists 'Big Watt Mustang Power', Williamson County, Big Watt Power Mustang LLC, gas, 448.98 MW, projected Dec 2028. ERCOT does not name the data center; the campus was formerly called Project Mustang and Big Watt is a developer. ercot.com ↗
- News report TCEQ air permit application for on-site natural gas generators (received): TCEQ told CBS Austin it has received Big Watt Digital's air permit application for the campus's natural gas electric generators but has not begun technical review. Permit number not stated; TCEQ record not opened. cbsaustin.com ↗
Water
- Official record Reclaimed-water closed-loop cooling; TCEQ wastewater application to be withdrawn: Proposed development agreement: closed-loop cooling using reclaimed water; developers to withdraw their TCEQ wastewater discharge permit application (City of Taylor). taylortx.gov ↗
Power plant permits tied to this project
- Air permit pending Big Watt Digital power units (Taylor)
Land, jobs & economic impact
Related records
CBS Austin: TCEQ says it received Big Watt Digital's air permit application for on-site gas generators; technical review not begun.
Source: cbsaustin.com ↗DCD: PowerHouse and Big Watt secured Taylor City Council approval for up to 1 GW campus with 750 MW on-site gas; first power targeted 1H 2028 (company plans via DCD).
Source: datacenterdynamics.com ↗KUT: council unanimously approved agreement with Big Watt/PowerHouse covering water, noise and air-quality conditions for the 664-acre campus.
Source: kut.org ↗Agenda item 6: council to consider development agreement for 664.39-acre Taylor Technology Campus (formerly Project Mustang); agenda posted Oct 2.
Source: taylortx.api.civicclerk.com ↗CBS Austin: Taylor City Council approves Taylor Technology Campus development agreement 5-0 ("unanimously"); formal annexation is a later step under the agreement.
Source: cbsaustin.com ↗Taylor Press: council unanimously approved the development agreement after public comment; no tax incentives; annexation expected later.
Source: taylorpress.net ↗City of Taylor publishes proposed development agreement for 664-acre Taylor Technology Campus; council to vote on the agreement Oct 8; no tax abatements requested.
Source: taylortx.gov ↗KUT: Taylor council to vote Oct 8 on deal to annex Big Watt/PowerHouse data center site and set conditions.
Source: kut.org ↗Sources
- Official record taylortx.gov
- News report kut.org
- News report cbsaustin.com
- News report taylorpress.net
- News report wilcolibertyproject.net
- Official record taylortx.api.civicclerk.com
- Official record taylortx.api.civicclerk.com
- News report datacenterdynamics.com
Free