Blueprint Projects Data Center (BPP Projects LLC, southeast Taylor)
BPP Projects LLC / Blueprint Data Centers; site bought by NCP Travis TPP Project LLC, the project's investor (Taylor Press)
- Status
- Approved (Chapter 380 agreement; Employment Center plan)
- Developer / parties
- BPP Projects LLC / Blueprint Data Centers; site bought by NCP Travis TPP Project LLC, the project's investor (Taylor Press)
- Location
- Taylor (southeast side, inside Carlos G Parker Blvd between Martin Luther King Blvd and the railroad tracks), Williamson County
- Size
- 135,000 sq ft, three buildings, electricity substation, backup generators, closed-loop cooling (City of Taylor); 60 MW gross utility capacity, energization 2026 and 2027 (company website)
- Investment
- $1 billion total over three phases (City of Taylor); minimum capital investment of $225,000,000 under the agreement (Taylor EDC)
- Reported benefits
- Ten-year 50% tax rebate for each construction phase, including tangible property in the data center; 50% rebate of local use tax on construction materials; minimum 5 jobs (Taylor EDC, Jun 2024)
- Concerns / impacts
- 1999 deed note said the land was to be held in trust for future parkland; the City says this was not a deed restriction (City of Taylor). Community protests, a lawsuit and an AG investigation; HALT Taylor Data Centers opposes (Taylor Press)
- Last verified
- 2026-11-01
Milestones
- Aug 2 2024 Taylor EDC board approved an agreement with BPP Projects LLC
- Aug 8 2024 City Council unanimously authorized a Chapter 380 economic development agreement with BPP Projects LLC
- Apr 11 2025 EDC sold the property to BPP Projects LLC for $10,000,000
- Jun 10 2025 P&Z approved the Employment Center Plan unanimously
- Jul 24 2025 City Council approved the Employment Center Plan unanimously (City of Taylor)
- residents' 2025 lawsuit to force parkland use was dismissed by the 395th District Court for lack of standing and is on appeal
- Sep 17 2026 Texas Attorney General announced an investigation into whether the site can legally be used for a data center (Taylor Press). Separate from taylor-tech-campus (Big Watt / PowerHouse).
Linked power & water
Land, jobs & economic impact
Related records
2026-09-17
State action News report
Taylor Press: AG Paxton is investigating whether the former parkland site in southeast Taylor can legally host the Blueprint Projects data center.
Source: taylorpress.net ↗2024-08-08
Tax abatement Official record
Taylor City Council unanimously authorized a Chapter 380 economic development agreement with BPP Projects LLC for the Blueprint Projects data center (city page).
Source: taylortx.gov ↗Sources
- Official record taylortx.gov
- News report tayloredc.org
- News report taylorpress.net
- News report blueprint-dc.com