Compass Datacenters Red Oak – Oglesby Road Campus (PD-194)
Compass Datacenters (company page; WFAA and FOX 4 name Compass); zoning request filed by William Dahlstrom (city agenda)
In short: Location: Red Oak (367 Oglesby Road, off FM 2377, per Compass), Ellis County, Texas. Status: Approved (PD-194 rezoning, Nov 17 2026, 4-1 per WFAA and FOX 4; city minutes not yet posted). Developer or parties: Compass Datacenters (company page; WFAA and FOX 4 name Compass); zoning request filed by William Dahlstrom (city agenda). Size: About 886.5 acres rezoned to PD-194 (city agenda); 10 buildings, 400 MW, on about 400 acres of an 867-acre site with a 100-acre public park (company claim). Latest record (Nov 17, 2026): WFAA: Red Oak approved 4-1 the PD-194 rezoning expanding Compass's data center campus to about 886 acres; lawsuit over May approval pending. Last verified Nov 18, 2026.
- Status
- Approved (PD-194 rezoning, Nov 17 2026, 4-1 per WFAA and FOX 4; city minutes not yet posted)
- Developer / parties
- Compass Datacenters (company page; WFAA and FOX 4 name Compass); zoning request filed by William Dahlstrom (city agenda)
- Location
- Red Oak (367 Oglesby Road, off FM 2377, per Compass), Ellis County
- Size
- About 886.5 acres rezoned to PD-194 (city agenda); 10 buildings, 400 MW, on about 400 acres of an 867-acre site with a 100-acre public park (company claim)
- Reported benefits
- Compass says it would fund a dedicated on-site substation and a switching station with Oncor, and use closed-loop/air cooling with no city water for cooling (company claim)
- Concerns / impacts
- Residents cite noise, light, loss of rural character and the environment; lawsuit over the May rezoning pending (WFAA; FOX 4)
- Last verified
- 2026-11-18
Milestones
- May 2026 Red Oak approved an earlier rezoning of the land
- a lawsuit over how the city approved it is pending (WFAA)
- Nov 5 2026 Compass community open house (company)
- Nov 17 2026 joint P&Z/City Council public hearing on ZC26-17, PD-191 and AG to PD-194 for Data Center Campus uses with concept plan, development regulations, landscaping, lighting and sound attenuation and a public park, Ordinance No. 26-038 (official agenda)
- approved 4-1 (WFAA; FOX 4). City says the request adds more of the applicant's parcels to the project approved in May (city spokesperson via WFAA). Compass says design and permitting would take 12-18 months after approval if ERCOT allocates power (company). Distinct from compass-red-oak (N. Austin Blvd campus)
Linked power & water
Power
- Company claim Dedicated on-site substation; planned switching station near the 138 kV line with Oncor: Compass says the 10-building, 400 MW campus would be served by a dedicated on-site substation it funds, plus a planned switching station near the existing 138 kV transmission line built with Oncor (company claim). compassdatacenters.com ↗
Land, jobs & economic impact
Related records
WFAA: Red Oak approved 4-1 the PD-194 rezoning expanding Compass's data center campus to about 886 acres; lawsuit over May approval pending.
Source: wfaa.com ↗Red Oak joint P&Z/Council hearing Nov 17, 7 p.m.: zoning change to PD-194 for a Data Center Campus on about 886.5 acres (ZC26-17).
Source: redoaktx.api.civicclerk.com ↗Sources
- Official record redoaktx.api.civicclerk.com
- News report wfaa.com
- News report fox4news.com
- News report compassdatacenters.com
Free
Get the free weekly digest for your county
Free weekly email every Friday for your first month, for 1 county you pick: new commissioners court actions, permits, filings and hearings, plus the week's top Texas changes. Every item links to its public source.
Same-day alerts come with Neighbor ($4/mo).