Ellis County · Just outside Grand Prairie
PowerHouse Data Centers; Provident Data Centers (co-developer)
Registered (TDLR)
Size: Company page: 810 acres, 8.5M developable sq ft, 1.8 GW max utility power (PowerHouse). Feb 2025 report: 768 acres, 24 buildings in three phases, 1.8 GW switchyard, first 500 MW tranche approved through ERCOT (Dallas Innovates)
Investment: Data Center Building 1 est. $72.6M (TDLR, as filed)
Last verified 2026-10-18 · 3 sources
Ellis County · Southern end of Midlothian, south of RailPort Business Park (news)
Digital Ranch LLC (city agenda); applicant Patrick Noonan of Merrell Capital (news)
Approved (city council actions Sep 22 2026)
Size: Three data centers, 3.9 million sq ft total; planned development on 395.7 acres of an 873.8-acre property (news)
Last verified 2026-10-18 · 2 sources
Ellis County · Midlothian (Railport Parkway)
Google, through Sharka LLC (TDLR owner; DCD identifies Sharka LLC as Google's shell company for the site)
Operating campus; Building 5 registered (TDLR)
Size: Building 5: new one-story 288,000 sq ft data center (TDLR). Building 4 (2024): 1-story 170,600 sq ft data center with central utility buildings (TDLR)
Investment: Building 5 est. $491.7M (TDLR, as filed); DCD reports $880M. Building 4 est. $350M (TDLR); DCD reported $100M
Last verified 2026-10-18 · 3 sources
Ellis County · Red Oak (330 N. Austin Blvd., per TDLR)
Alamo Mission LLC (TDLR owner; operator not named in the opened filings)
RED1A complete (TDLR Inspection Complete); RED2A registered (TDLR)
Size: RED1A: new data center, 170,594 sq ft; RED2A: new building, 285,310 sq ft (TDLR)
Investment: RED1A est. $176M; RED2A est. $176M (TDLR, as filed)
Last verified 2026-10-18 · 3 sources
Ellis County · Red Oak (Stainback Rd and Batchler Rd, per TDLR)
DataBank (TDLR owners Databank; DB Data Center Red Oak, LLC; DB Data Center Red Oak 12, LLC)
Existing campus; new buildings and fit-outs registered (TDLR)
Size: Two-story data centers with office: DFW11, DFW12, DFW13 425,170 sq ft each (Stainback Rd); DFW14 and DFW15 443,679 sq ft each (Batchler Rd); tenant fit-outs for DFW9–DFW12 (TDLR)
Investment: TDLR est. costs as filed: DFW11, DFW12, DFW13, DFW14 $325M each; DFW15 $425M; fit-outs DFW9 $200M, DFW10 $301M, DFW11 $315M, DFW12 $155M
Last verified 2026-10-18 · 9 sources
Ellis County · Red Oak (550–590 Austin Blvd, per TDLR)
Compass Datacenters (TDLR owners Compass Datacenters DFW IIIJ, IIIH and III-I LLC)
Registered (TDLR)
Size: Interior/tenant fit-outs of 251,815 sq ft each for Buildings 8, 9 and 10, new data centers on the campus (TDLR)
Investment: Est. $100M per building fit-out (TDLR, as filed)
Last verified 2026-10-18 · 3 sources