- Status
- SAT80–81 construction complete (TDLR); SAT82 registered (TDLR)
- Developer / parties
- Microsoft
- Location
- Castroville (18844 FM 1957 / Potranco Rd), Medina County
- Size
- SAT80 and SAT81: 106,012 sq ft each (admin building, Colo 1 finish-out, Colo 2 shell); SAT82: one-story, 5 colos, 244,676 sq ft (Jul 2024 filing at 18844 FM 1957). A Dec 2025 filing also named SAT82 lists 3580 FM 471 N, Castroville, 1-story 5-colo, 195,670 sq ft (TDLR TABS)
- Investment
- Est. cost SAT80 $135M, SAT81 $95M (TDLR TABS; Devine News puts the FM 1957 data center at $230M); SAT82 est. $482.6M (Jul 2024 filing) and $400M (Dec 2025 filing at 3580 FM 471 N) (TDLR TABS)
- Reported benefits
- Microsoft funds a county fire inspection program under a Chapter 381 agreement (minutes; agenda summary)
- Last verified
- 2026-10-06
Milestones
- Jul 28 2022 SAT80 and SAT81 construction start
- Jul 26 2023 SAT80 and SAT81 registered with TDLR
- May 13 2024 Commissioners Court approved 4-0 a Chapter 381 economic development agreement with Microsoft for a county fire inspection program (minutes)
- agenda summary: Microsoft contributes $100,000 for fire inspection of the data centers, 3-year term
- Devine News: $100,000 a year for inspections at the FM 1957 data center
- Jul 25 2024 SAT82 registered at 18844 FM 1957 (start Apr 11 2026, completion Feb 8 2028; status Review Complete)
- Aug 31 2024 SAT80 and Sep 30 2024 SAT81 completion dates, both TDLR status Inspection Complete
- Dec 17 2025 a second TDLR registration named Microsoft SAT82 at 3580 FM 471 N (start Aug 13 2026, completion Jul 24 2028; Project Registered)
- relation between the two SAT82 filings not stated. No TDLR registrations found for SAT83, SAT84 or SAT85 (TDLR search, Oct 6 2026)
Related records
TDLR TABS: 'Microsoft SAT82 Data Center' at 3580 FM 471 N, Castroville; 5 colos, 195,670 sq ft, $400M; start Aug 13 2026.
Source: tdlr.texas.gov ↗TDLR TABS: Microsoft SAT82, 18844 FM 1957; 5 colos, 244,676 sq ft, $482.6M; start Apr 11 2026, completion Feb 8 2028.
Source: tdlr.texas.gov ↗Minutes: court approves 4-0 a Chapter 381 agreement with Microsoft for a fire inspection program; agenda: $100,000, 3-year term.
Source: public.destinyhosted.com ↗TDLR TABS: Microsoft SAT80, 18844 FM 1957, Castroville; 106,012 sq ft, $135M; completed Aug 31 2024 (Inspection Complete).
Source: tdlr.texas.gov ↗TDLR TABS: Microsoft SAT81, 18844 FM 1957, Castroville; 106,012 sq ft, $95M; completed Sep 30 2024 (Inspection Complete).
Source: tdlr.texas.gov ↗Sources
- Official record tdlr.texas.gov
- Official record tdlr.texas.gov
- Official record tdlr.texas.gov
- Official record tdlr.texas.gov
- Official record public.destinyhosted.com
- News report devinenews.com