Home / Tarrant County / Project
Circle T Data Center (Circle T Ranch DAL130 Campus)
PowerHouse Data Centers (Dallas News: "designed by developer PowerHouse Data Centers"; PowerHouse-branded "PH Circle T [300 MW]" presentation to Westlake P&Z, company); owner Circle T Owner LP, 1999 Bryan St. Ste 900, Dallas (TDLR). DCD: listed owner Circle T Owner LP names AREP and PowerHouse CEO Doug Fleit as contact, and PowerHouse is a wholly-owned division of American Real Estate Partners (AREP) (news; this resolves the earlier AREP Westlake candidate as the same project)
In short: Location: Westlake (13572 N. Main St.), Tarrant County, Texas. Status: Approved (Westlake development agreement); registered (TDLR). Developer or parties: PowerHouse Data Centers (Dallas News: "designed by developer PowerHouse Data Centers"; PowerHouse-branded "PH Circle T [300 MW]" presentation to Westlake P&Z… Size: Four buildings on ~88 acres (Dallas News); 94 net developable acres, 300 MW / Oncor (PowerHouse presentation to Westlake P&Z, Aug 4 2026; company figure); TDLR: DAL130 data… Investment: TDLR est. costs: data center building $83M; auxiliary water building $45M; access control building $15M. Latest record (Nov 12, 2026): NE Tarrant Record: Westlake Town Council special meeting Nov 12, 5 p.m., to vote on the Circle T data center development agreement. Last verified Oct 15, 2026.
- Status
- Approved (Westlake development agreement); registered (TDLR)
- Developer / parties
- PowerHouse Data Centers (Dallas News: "designed by developer PowerHouse Data Centers"; PowerHouse-branded "PH Circle T [300 MW]" presentation to Westlake P&Z, company); owner Circle T Owner LP, 1999 Bryan St. Ste 900, Dallas (TDLR). DCD: listed owner Circle T Owner LP names AREP and PowerHouse CEO Doug Fleit as contact, and PowerHouse is a wholly-owned division of American Real Estate Partners (AREP) (news; this resolves the earlier AREP Westlake candidate as the same project)
- Location
- Westlake (13572 N. Main St.), Tarrant County
- Size
- Four buildings on ~88 acres (Dallas News); 94 net developable acres, 300 MW / Oncor (PowerHouse presentation to Westlake P&Z, Aug 4 2026; company figure); TDLR: DAL130 data center building 224,152 sq ft, auxiliary water building 5,000 sq ft, access control building 1,500 sq ft
- Investment
- TDLR est. costs: data center building $83M; auxiliary water building $45M; access control building $15M
- Concerns / impacts
- Keller HOA, two individuals and the City of Keller allege zoning and notice violations, incl. an omitted 150-ft setback/buffer (lawsuit, per CBS Texas); Keller residents say the site is hundreds of feet from their homes (Dallas News)
- Last verified
- 2026-10-15
Milestones
- Aug 4 2026 Westlake Planning and Zoning Commission voted to recommend the data center (Dallas News)
- Aug 17 2026 judge issued a TRO forcing the Town Council to table a vote linked to the project
- Sep 25 2026 TRO dissolved and hearing set for Oct 23 2026 on whether plaintiffs have standing (Dallas News; CBS Texas)
- Oct 2 2026 three DAL130 buildings registered with TDLR (start Dec 1 2026, completion Jun 1 2027). TDLR address (13572 N. Main St.) matches the address in the PowerHouse Circle T presentation. Westlake says the land has been zoned commercial/industrial since 1998 (Dallas News)
- Nov 5 2026 settlement among the developer, Keller and the Keller HOA ended the neighbors' lawsuit (CBS Texas; WFAA)
- Nov 12 2026 Westlake Town Council approved the developer's agreement, Resolution 26-36, as presented (Town of Westlake recap)
Linked power & water
Power
- Official record New 350 MW Oncor substation near the Town pump station, paid by developer: Project funds a new 350-megawatt substation near the Town's pump station, paid entirely by the developer; developer prepaid Oncor for the electrical infrastructure (Town of Westlake FAQ). westlake-tx.org ↗
Water
- Official record Town of Westlake water (Fort Worth / Tarrant Regional Water District); pump station upgrade: Campus expected to use ~54 million gallons a year; developer pays to enlarge waterlines and pump station equipment (capacity 7.5 → 10 MGD); 1.5 million gallons kept on site; tenant to replenish 100% of cooling water (Town of Westlake FAQ). westlake-tx.org ↗
Land, jobs & economic impact
Related records
NE Tarrant Record: Westlake Town Council special meeting Nov 12, 5 p.m., to vote on the Circle T data center development agreement.
Source: netarrantrecord.com ↗Town of Westlake: after public comment, Town Council approved the Circle T data center developer's agreement (Resolution 26-36) as presented.
Source: westlake-tx.org ↗CBS Texas: Keller approves Circle T settlement (noise limits, 10-ft berm, $1.5M fund, $300K fire, Tier 4 generators); HOA ends suit; Westlake approval still needed.
Source: cbsnews.com ↗TDLR TABS: 'DAL130 – Data Center', 224,152 sq ft, est. $83M, Circle T Ranch DAL130 Campus, Westlake; owner Circle T Owner LP.
Source: tdlr.texas.gov ↗Judge dissolves TRO in Keller HOA/City of Keller suit against Westlake over Circle T Data Center; standing hearing set Oct 23 (Dallas News).
Source: dallasnews.com ↗CBS Texas: Tarrant County judge dissolves TRO and sets Oct 23 hearing on Westlake Circle T data center suit; Westlake spokesman says dispute should be resolved then.
Source: cbsnews.com ↗Sources
- Official record westlake-tx.org
- Official record tdlr.texas.gov
- Official record tdlr.texas.gov
- Official record tdlr.texas.gov
- News report dallasnews.com
- News report cbsnews.com
- Official record westlake-tx.org
- News report datacenterdynamics.com
Free
Get the free weekly digest for your county
Free weekly email every Friday for your first month, for 1 county you pick: new commissioners court actions, permits, filings and hearings, plus the week's top Texas changes. Every item links to its public source.
Same-day alerts come with Neighbor ($4/mo).