Is Texas banning data centers? Not yet. Here's what's actually paused.

Posts this week say Texas has "stopped" data centers. The records say something narrower: state grid studies and new energizations for big loads, and state environmental permits, are paused during an audit. Local governments are still voting on projects. A broader moratorium is a campaign pledge from the governor-elect, who takes office Jan 19.

Every item below links to its source and is labeled official record, company claim or news report. Newest item check: 2026-11-17.

Free · every Friday

Get updates for your county

New filings, votes and hearings for the county you pick, in one email every Friday, free for your first month. Free accounts cover 1 county. Want it same-day? Neighbor, $4/mo, first 30 days free.

Sample

New commissioners court record · Brazos County

Record date 2026-11-17 · Official record

Brazos County Nov 17 agenda: action on assigning the Second Amendment to the RELLIS Campus Data and Research Center tax abatement. Outcome not yet posted.

Project: ThisWay Global Research and AI Compute Center (former RELLIS Campus Data and Research Center)

Read the public source: brazos.primegov.com ↗

Sample of the alert format, using a real public record. The record date is not in the future. Last checked 2026-11-17.

Paused right now (state level)

What the Governor's August and September directives paused, per ERCOT, the Governor's office and TCEQ.

2026-08-03
Grid/ERCOT Official record Statewide

ERCOT market notice pauses Batch Zero study, delays Large Load classification, pauses energization approvals for data centers/crypto ≥75 MW.

Source: ercot.com ↗
2026-09-14
Grid/ERCOT Official record Statewide

ERCOT market notice M-B091426-01: State and Community Impact RFI for data centers ≥25 MW; responses due 5 p.m. Oct 12 2026; report by Dec 10.

Source: ercot.com ↗
2026-09-21
State action Official record Statewide

Gov. Abbott directs TCEQ to halt all permits sought by data centers until ERCOT and TWDB audits finish; TCEQ compliance update due Oct 19.

Source: gov.texas.gov ↗
2026-10-19
State action Official record Statewide

TCEQ letter to Governor (Oct 19 compliance update): permits for infrastructure directly supporting data centers paused; pending applications screened; claimed authorizations suspended where possible.

Source: tceq.texas.gov ↗

What could come next

Election results and the governor-elect's stated plans. Statements are not law or agency action.

2026-10-22
Incoming official statement News report Statewide

Campaign statement (Texas Tribune): Hinojosa said as governor she will issue a moratorium on all data center approvals until the Legislature passes protections; takes office Jan 19.

Source: texastribune.org ↗
2026-11-03
Election result Official record Statewide

SOS unofficial results (100% of polling locations, updated Nov 4): Hinojosa (D) governor, Goodwin (D) Lt. Gov., Johnson (D) AG, Eckhardt (D) comptroller; canvass pending.

Source: electionresults.sos.state.tx.us ↗
2026-11-05
Incoming official statement News report Statewide

Post-election (CNN via USA Today): Gov.-elect Hinojosa says 'we need to stop what we are doing with data centers until we have those protections'; not against data centers.

Source: usatoday.com ↗
Undated
Incoming official statement News report Statewide

Hinojosa campaign platform page (checked Nov 9): immediate moratorium on new data centers until the Legislature acts; end HB 2712 (2015) data center tax breaks.

Source: ginafortexas.com ↗

Still moving locally

Recent local votes, hearings and company announcements. Local approvals don't replace state grid and permit steps.

2026-11-12
City council Official record Tarrant County · Circle T Data Center (Circle T Ranch DAL130 Campus)

Town of Westlake: after public comment, Town Council approved the Circle T data center developer's agreement (Resolution 26-36) as presented.

Source: westlake-tx.org ↗
2026-11-12
Company announcement News report Cameron County · SpaceX Starbase gas-fired power plant and super-compute facility

SpaceX: $24B+ Starbase supercompute facility will generate its own power off the public grid; 3,000+ construction, 500+ permanent jobs (company claim).

Source: spacex.com ↗
2026-11-10
City council News report Lubbock County

Lubbock council held first of two hearings on 90-day data center moratorium, no vote; second hearing and first possible vote Dec 10; P&Z rules to council Dec 1 (KCBD).

Source: kcbd.com ↗
2026-11-09
Commissioners court News report Cottle County · Project Matter (RS 70 Land Holdings Reinvestment Zone, Triangle Ranch)

SL Tribune: commissioners unanimously approved the 4,252-acre reinvestment zone and Aetheris tax abatement; 90-day clock for development and payments starts.

Source: sltrib.com ↗
2026-11-06
Tax abatement News report Cameron County · SpaceX Starbase gas-fired power plant and super-compute facility

Starbase notice: Dec. 9 hearing on a Chapter 312 tax abatement and related Chapter 380 agreement for SpaceX's proposed gas-fired power plant and super-compute facility.

Source: cdn.prod.website-files.com ↗

Bills filed for the 2027 session

Prefiled bills that would change data center tax breaks, grid costs and water reporting. Filing is not passage.

2026-11-09
Legislation Official record Statewide

Prefiled SB 293 (Huffman and others): repeal of sales and use tax exemptions for property used in certain data centers and large data center projects.

Source: capitol.texas.gov ↗
2026-11-09
Legislation Official record Statewide

Prefiled HB 730 (Vincent Perez): large-load interconnection and recovery of generation costs for large load customers; HB 732: data center incentive ineligibility.

Source: capitol.texas.gov ↗
2026-11-12
Legislation Official record Statewide

Filed SB 338 (Perry and others): water-efficient cooling and water reporting in data center tax deals, 50% city abatement cap, PUC disconnect rules.

Source: capitol.texas.gov ↗

Key dates

Dates from posted notices and agency filings in our tracker. Agendas and schedules can change.

Dec 9, 2026

Starbase City Commission hearing on a tax abatement and Chapter 380 deal for SpaceX's proposed gas-fired power plant and supercompute facility

Related records →
Dec 10, 2026

ERCOT data center audit report due (State and Community Impact review)

Related records →
Dec 14, 2026

Comments and hearing requests due at the PUC on the proposed standard large-load interconnection agreement (Project 59999)

Related records →
Jan 12, 2027

90th Texas Legislature convenes

Related records →
Jan 19, 2027

Governor-elect Hinojosa takes office (per Texas Tribune)

Related records →

Frequently asked questions

Is Texas banning data centers?

Not as of 2026-11-17. No state law bans data centers. Since August 2026 ERCOT has paused studies and new energization approvals for large loads of 75 MW and up during a Governor-ordered audit, and since Sep 21 TCEQ has paused permits for infrastructure directly supporting data centers. Governor-elect Gina Hinojosa has pledged a moratorium on new approvals after she takes office, until the Legislature passes protections.

Are data center projects still being approved in Texas?

Yes, at the local level. For example, the Town of Westlake approved the Circle T data center developer's agreement on Nov 12, 2026, and Cottle County commissioners approved a reinvestment zone and tax abatement for Aetheris Project Matter on Nov 9, 2026 (news report). Local approvals do not replace state grid and permit steps.

When does the current pause end?

No end date has been announced. ERCOT's audit report is due Dec 10, 2026. Check the records below for changes.