Home / Counties / Cameron

Data centers in Cameron County, Texas

1 project · 1 unconfirmed lead and 7 dated records · last verified 2026-10-22

Free · every Friday

Get Cameron County updates free

New filings, votes and hearings in Cameron County, in one email every Friday, free for your first month. Free accounts cover 1 county. Want it same-day? Neighbor, $4/mo, first 2 months free.

Upcoming hearings & deadlines

2026-11-04
City council News report

MyRGV: Brownsville passed first reading of a 90-day data center moratorium Oct 7 (unanimous); second reading Nov 4, effective Nov 5.

Source: myrgv.com ↗

Projects

Cameron County · Near Harlingen / Rio Hondo (unincorporated; east of FM 509, west of FM 106, near Valley International Airport)

Fluidstack Cameron County AI data center campus

Fluidstack

Under construction

Size: First phase planned to support up to 1.5 GW (company); more than 1,100 acres (KRGV, citing company release)

Investment: $4B first phase (company)

Last verified 2026-10-22 · 4 sources

Leads (unconfirmed)

Leads are credible signals that don't yet meet our rule for a tracked project (two independent sources or one official record): sites marketed for sale, crypto mines, and news-only or company-claim projects with no filings. Each claim is labeled. We move a lead into the project list when an official record appears.

Cameron County · Harlingen area · Company claim

Eneus Energy RGV Data Center (Harlingen area)

Eneus Energy

Lead / unconfirmed Proposed (company claim); records lawsuit pending

Size: Up to 2 GW, 16 data halls on 1,785 acres; planned 765 kV transmission line (company claim)

  • Company claim Eneus project page: 1,785-acre site in Cameron County, up to 2 GW of total power capacity, 16 data halls, a planned 765 kV transmission line and 'capability for more generation'. eneusenergy.com ↗
  • News report DCD restates the company's 2 GW / 1,785-acre plan and its claimed $14B capital investment. datacenterdynamics.com ↗
  • News report RGV Business Journal (May 24 2026): Eneus sued Cameron County and the Texas Attorney General on May 13 in Travis County to block release of project records requested Jan 8 (timelines, water, power, incentives). rgvbusinessjournal.com ↗

Last checked 2026-10-18. Not counted in our project totals until an official record confirms it.

Records & actions

2026-11-04
City council News report

MyRGV: Brownsville passed first reading of a 90-day data center moratorium Oct 7 (unanimous); second reading Nov 4, effective Nov 5.

Source: myrgv.com ↗
2026-10-21
City council Official record · Fluidstack Cameron County AI data center campus

Harlingen agenda item 10n (Oct 21, 5:30 p.m.): interlocal drainage maintenance and flood control agreement with Cameron County; agenda does not name Fluidstack.

Source: harlingentx.api.civicclerk.com ↗
2026-10-20
News News report · Fluidstack Cameron County AI data center campus

MyRGV: county voted 3-1 Oct 6 for a drainage interlocal with Harlingen; $7M canal widening paid by Fluidstack for its stormwater; Harlingen votes Oct 21.

Source: myrgv.com ↗
2026-09-21
Company announcement News report · Fluidstack Cameron County AI data center campus

Fluidstack: construction begun on $4B first phase planned for up to 1.5 GW; closed-loop cooling; no abatements requested (company).

Source: fluidstack.io ↗
2026-09-10
County permit Official record · Fluidstack Cameron County AI data center campus

Cameron County issues Fluidstack worksite permit for site work near Valley International Airport; building permits still required; no county tax abatement.

Source: cameroncountytx.gov ↗
2026-09-10
News News report · Fluidstack Cameron County AI data center campus

KRGV: Fluidstack starts $4B first phase on 1,100+ acres; Harlingen had tabled a canal drainage deal; Rep. Gonzalez opposes over water.

Source: krgv.com ↗
2026-09-02
City council Official record · Fluidstack Cameron County AI data center campus

Harlingen minutes: Fluidstack stormwater discharge agreement tabled unanimously pending a town hall; 4-1 resolution requires commission approval of outside-city drain connections.

Source: harlingentx.api.civicclerk.com ↗

Spot an error or a missing filing? Email [email protected] with the source link.