Home / Shackelford County / Project

Vantage "Frontier" mega-campus

Vantage Data Centers

In short: Location: Albany area, Shackelford County, Texas. Status: Under construction. Developer or parties: Vantage Data Centers. Size: 1.4 GW; ~1,200 acres; 10 buildings, ~3.7M sq ft. Investment: $25B. Latest record (Sep 22, 2026): Public Citizen: TCEQ mailed a preliminary-decision notice Sep 22 for VoltaGrid's ABI-1 plant; newspaper notice receipt logged Sep 28; no comment deadline set. Last verified Oct 3, 2026.

Status
Under construction
Developer / parties
Vantage Data Centers
Location
Albany area, Shackelford County
Size
1.4 GW; ~1,200 acres; 10 buildings, ~3.7M sq ft
Investment
$25B
Reported benefits
Proposed terms: $10M/yr payments in lieu of property taxes for 10 years; $150,000/yr to local charities for 10 years; up to 10 scholarships/yr (Albany News). KTAB/KRBC: company "will pay 10 million for the first 10 years and pay the tax rate for the following seven years" (agreement itself not seen)
Last verified
2026-10-03

Milestones

Figures are attributed in parentheses to the outlet or company that reported them. Where sources disagree, we show both.

  1. Jul 2025 Commissioners Court unanimously created Reinvestment Zone 2025-1, accepted Vantage's abatement application and stated intent to sign a formal agreement once land is purchased (Albany News, Jul 24 2025)
  2. county judge: agreement to be formalized after property transfer (KTAB/KRBC, Jul 31 2025). Signed agreement not confirmed by any opened source. Aug 2025 Frontier announced (Vantage). Jun 29–30 2026 TDLR registrations for "Vantage DC Abilene – TX3 – Project Frontier" buildings TX301–TX311 (TDLR search), e.g., TX304: 453,385 sq ft, est. $1.315B, start Sep 26 2025, completion May 18 2027, status Review Complete (TDLR)

Linked power & water

Power

  • Official record VoltaGrid ABI-1 Electric Generating Facility (TCEQ 182467 / PSDTX1692 / GHGPSDTX266): Dec 12 2025 VoltaGrid applied to TCEQ for a gas engine power plant at 299 FM 604, Shackelford County; power to be used on site and by the nearby data center campus; pending as of Oct 18 2026 (TCEQ). tceq.texas.gov ↗
  • News report VoltaGrid behind-the-meter gas microgrid (~700 MW first phase): Vantage and VoltaGrid confirmed their roles; TCEQ documents show VoltaGrid approved for 210 gas generators totaling 700 MW near the site, for the first construction phase (Business Insider). businessinsider.com ↗
  • News report VoltaGrid ABI-1: preliminary decision notice mailed Sep 22 2026: TCEQ mailed the notice of preliminary decision Sep 22; comment deadline not yet set (Public Citizen, citing TCEQ records). citizen.org ↗

Water

  • Company claim Closed-loop chiller system, near-zero WUE: Closed-loop chilled water system requiring minimal water for cooling; water utilization efficiency near zero (Vantage). web.archive.org ↗

Power and water projects tied to this data center: on-site or dedicated generation, utility and grid capacity deals, substations, water supply, reclaimed water and wastewater permits. Each item is labeled by source type.

Land, jobs & economic impact

Jobs and economic impact

  • Company claim Jul 24, 2025 · Stated figure (company, via news) · 250 permanent jobs stated by the company, not confirmed as jobs already created · 6,500 construction jobs stated by the company, not confirmed as jobs already created: At the Jul 2025 commissioners court hearing, Vantage's representatives said the project is expected to create 250 full-time jobs with an annual payroll of $25 million, and up to 6,500 workers on site at peak construction. Vantage agreed to a 10-year abatement with $10 million a year in payments in lieu of taxes and $150,000 a year to local charities. The agreement was to be signed after the land purchase; we have not confirmed it was. thealbany.news ↗ (Albany News report of the commissioners court hearing; checked Oct 28, 2026)

Reported, not counted

  • News report Albany News reported in Jul 2025 that Vantage still had to buy about 1,200 acres, and that the abatement agreement would be signed once the land transaction was complete. We have not found the deed or a signed agreement. thealbany.news ↗

Land rows come only from deeds, appraisal district or abatement filings, government agreements or SEC filings. Job and dollar figures are the ones stated in agreements, filings or releases. A commitment, target, or company statement is not a count of jobs already created. These rows were not refreshed with the November 7 record update; each row shows the date it was checked. Members get the statewide roll-up in the members area.

Related records

2026-09-22
TCEQ permit News report Shackelford County · Vantage "Frontier" mega-campus

Public Citizen: TCEQ mailed a preliminary-decision notice Sep 22 for VoltaGrid's ABI-1 plant; newspaper notice receipt logged Sep 28; no comment deadline set.

Source: citizen.org ↗
2026-06-29
Building registration (TDLR) Official record Shackelford County · Vantage "Frontier" mega-campus

TDLR TABS: Vantage 'TX3 – Project Frontier' building TX304, 453,385 sq ft, est. $1.315B; one of buildings TX301–TX311 registered Jun 29–30.

Source: tdlr.texas.gov ↗
2025-12-12
TCEQ permit Official record Shackelford County · Vantage "Frontier" mega-campus

VoltaGrid submitted TCEQ air application 182467 for the ABI-1 Electric Generating Facility at 299 FM 604, serving the nearby data center campus.

Source: tceq.texas.gov ↗
2025-07-24
Tax abatement News report Shackelford County · Vantage "Frontier" mega-campus

Albany News: county creates Reinvestment Zone 2025-1, accepts Vantage abatement application; agreement to be signed after land purchase.

Source: thealbanynews.net ↗

Sources

Found an error? Email [email protected] with a source link.