Home / Shackelford County / Project
Vantage "Frontier" mega-campus
Vantage Data Centers
In short: Location: Albany area, Shackelford County, Texas. Status: Under construction. Developer or parties: Vantage Data Centers. Size: 1.4 GW; ~1,200 acres; 10 buildings, ~3.7M sq ft. Investment: $25B. Latest record (Sep 22, 2026): Public Citizen: TCEQ mailed a preliminary-decision notice Sep 22 for VoltaGrid's ABI-1 plant; newspaper notice receipt logged Sep 28; no comment deadline set. Last verified Oct 3, 2026.
- Status
- Under construction
- Developer / parties
- Vantage Data Centers
- Location
- Albany area, Shackelford County
- Size
- 1.4 GW; ~1,200 acres; 10 buildings, ~3.7M sq ft
- Investment
- $25B
- Reported benefits
- Proposed terms: $10M/yr payments in lieu of property taxes for 10 years; $150,000/yr to local charities for 10 years; up to 10 scholarships/yr (Albany News). KTAB/KRBC: company "will pay 10 million for the first 10 years and pay the tax rate for the following seven years" (agreement itself not seen)
- Last verified
- 2026-10-03
Milestones
- Jul 2025 Commissioners Court unanimously created Reinvestment Zone 2025-1, accepted Vantage's abatement application and stated intent to sign a formal agreement once land is purchased (Albany News, Jul 24 2025)
- county judge: agreement to be formalized after property transfer (KTAB/KRBC, Jul 31 2025). Signed agreement not confirmed by any opened source. Aug 2025 Frontier announced (Vantage). Jun 29–30 2026 TDLR registrations for "Vantage DC Abilene – TX3 – Project Frontier" buildings TX301–TX311 (TDLR search), e.g., TX304: 453,385 sq ft, est. $1.315B, start Sep 26 2025, completion May 18 2027, status Review Complete (TDLR)
Linked power & water
Power
- Official record VoltaGrid ABI-1 Electric Generating Facility (TCEQ 182467 / PSDTX1692 / GHGPSDTX266): Dec 12 2025 VoltaGrid applied to TCEQ for a gas engine power plant at 299 FM 604, Shackelford County; power to be used on site and by the nearby data center campus; pending as of Oct 18 2026 (TCEQ). tceq.texas.gov ↗
- News report VoltaGrid behind-the-meter gas microgrid (~700 MW first phase): Vantage and VoltaGrid confirmed their roles; TCEQ documents show VoltaGrid approved for 210 gas generators totaling 700 MW near the site, for the first construction phase (Business Insider). businessinsider.com ↗
- News report VoltaGrid ABI-1: preliminary decision notice mailed Sep 22 2026: TCEQ mailed the notice of preliminary decision Sep 22; comment deadline not yet set (Public Citizen, citing TCEQ records). citizen.org ↗
Water
- Company claim Closed-loop chiller system, near-zero WUE: Closed-loop chilled water system requiring minimal water for cooling; water utilization efficiency near zero (Vantage). web.archive.org ↗
Land, jobs & economic impact
Jobs and economic impact
- Company claim Jul 24, 2025 · Stated figure (company, via news) · 250 permanent jobs stated by the company, not confirmed as jobs already created · 6,500 construction jobs stated by the company, not confirmed as jobs already created: At the Jul 2025 commissioners court hearing, Vantage's representatives said the project is expected to create 250 full-time jobs with an annual payroll of $25 million, and up to 6,500 workers on site at peak construction. Vantage agreed to a 10-year abatement with $10 million a year in payments in lieu of taxes and $150,000 a year to local charities. The agreement was to be signed after the land purchase; we have not confirmed it was. thealbany.news ↗
Reported, not counted
- News report Albany News reported in Jul 2025 that Vantage still had to buy about 1,200 acres, and that the abatement agreement would be signed once the land transaction was complete. We have not found the deed or a signed agreement. thealbany.news ↗
Related records
Public Citizen: TCEQ mailed a preliminary-decision notice Sep 22 for VoltaGrid's ABI-1 plant; newspaper notice receipt logged Sep 28; no comment deadline set.
Source: citizen.org ↗TDLR TABS: Vantage 'TX3 – Project Frontier' building TX304, 453,385 sq ft, est. $1.315B; one of buildings TX301–TX311 registered Jun 29–30.
Source: tdlr.texas.gov ↗VoltaGrid submitted TCEQ air application 182467 for the ABI-1 Electric Generating Facility at 299 FM 604, serving the nearby data center campus.
Source: tceq.texas.gov ↗Albany News: county creates Reinvestment Zone 2025-1, accepts Vantage abatement application; agreement to be signed after land purchase.
Source: thealbanynews.net ↗Sources
- Company claim vantage-dc.com
- News report thealbanynews.net
- News report yahoo.com
- Official record tdlr.texas.gov
Free
Get the free weekly digest for your county
Free weekly email every Friday for your first month, for 1 county you pick: new commissioners court actions, permits, filings and hearings, plus the week's top Texas changes. Every item links to its public source.
Same-day alerts come with Neighbor ($4/mo).