Caldwell Valley Technology Park

Tract

In short: Location: Lockhart (north of), Caldwell County, Texas. Status: Proposed / in development. Developer or parties: Tract. Size: ~3,000 acres; 'more than 4GW' (Tract release body; its subhead says 'up to 4GW'); 'over 4GW' (Caldwell County recap); first 250 MW contracted for delivery Q1 2028 (Tract). Latest record (Sep 22, 2026): Public Citizen: TCEQ issued construction stormwater coverage Sep 22 to Ranger Excavating for Caldwell Valley Technology Park, 727 Farmers Road, Maxwell. Last verified Oct 3, 2026.

Status
Proposed / in development
Developer / parties
Tract
Location
Lockhart (north of), Caldwell County
Size
~3,000 acres; 'more than 4GW' (Tract release body; its subhead says 'up to 4GW'); 'over 4GW' (Caldwell County recap); first 250 MW contracted for delivery Q1 2028 (Tract)
Concerns / impacts
Water use; county seeks transparency, independent impact analysis and county/municipal authority (Resolution 29-2026, statewide; does not name Tract)
Last verified
2026-10-03

Milestones

Figures are attributed in parentheses to the outlet or company that reported them. Where sources disagree, we show both.

  1. Jan 13 2026 Tract added 1,458 acres to its existing 1,515-acre park (Tract)
  2. Mar 12 2026 county workshop on data centers, county recap names Tract's ~3,000-acre park north of Lockhart (official county site)
  3. May 14 2026 Caldwell County Resolution 29-2026 (statewide in scope; does not name Tract) opposes high-water-use cooling in water-constrained regions, urges state reporting requirements, and asks the Legislature to give counties and municipalities authority over data center land use

Linked power & water

Power

  • Company claim On-site Bluebonnet/LCRA substation (scalable to 1.6 GW; first 250 MW contracted for Q1 2028): Tract, Bluebonnet and LCRA are planning an onsite substation capable of scaling to 1.6 GW, first 250 MW contracted for Q1 2028 delivery (Tract, Jan 13 2026). tract.com ↗
  • Company claim Planned on-site power generation (grid-connected): Tract has initiated plans for onsite power generation that will become grid connected (Tract, Jan 13 2026); type and size not stated. tract.com ↗

Power and water projects tied to this data center: on-site or dedicated generation, utility and grid capacity deals, substations, water supply, reclaimed water and wastewater permits. Each item is labeled by source type.

Land, jobs & economic impact

No land purchase, jobs or economic impact figure from a deed, agreement, filing or company release has been found for this project yet.

Related records

2026-09-22
TCEQ permit News report Caldwell County · Caldwell Valley Technology Park

Public Citizen: TCEQ issued construction stormwater coverage Sep 22 to Ranger Excavating for Caldwell Valley Technology Park, 727 Farmers Road, Maxwell.

Source: citizen.org ↗
2026-03-12
Commissioners court Official record Caldwell County · Caldwell Valley Technology Park

County recap of Mar 12 data center workshop: Tract developing ~3,000-acre park north of Lockhart; county influence over development limited.

Source: co.caldwell.tx.us ↗
2026-01-13
Company announcement Company claim Caldwell County · Caldwell Valley Technology Park

Tract adds 1,458 acres to Caldwell Valley Technology Park (~3,000 acres total); first 250 MW contracted for Q1 2028.

Source: tract.com ↗

Sources

Found an error? Email [email protected] with a source link.

Free

Get the free weekly digest for your county

Free weekly email every Friday for your first month, for 1 county you pick: new commissioners court actions, permits, filings and hearings, plus the week's top Texas changes. Every item links to its public source.

Same-day alerts come with Neighbor ($4/mo).