Home / Taylor County / Project

Stargate I / Crusoe Abilene AI Campus (Lancium Clean Campus)

Crusoe (builder); Lancium (land/power); Oracle for OpenAI

In short: Location: Abilene, Taylor County, Texas. Status: Partially operational. Developer or parties: Crusoe (builder); Lancium (land/power); Oracle for OpenAI. Size: ~1.2 GW, 8 buildings, ~4M sq ft. Investment: $30–33B total construction cost, all phases (per CNR). Latest record (Aug 13, 2026): CNR: DPR building current Abilene phase; buildings complete end-2026, closeout early 2027; up to 5,000 workers at peak. Last verified Oct 18, 2026.

Status
Partially operational
Developer / parties
Crusoe (builder); Lancium (land/power); Oracle for OpenAI
Location
Abilene, Taylor County
Size
~1.2 GW, 8 buildings, ~4M sq ft
Investment
$30–33B total construction cost, all phases (per CNR)
Reported benefits
Worker counts differ: ~9,000 craft workers on site daily (Crusoe SVP via KTXS, Mar 5 2026); up to 5,000 workers at spring/summer 2026 peak (CNR, Aug 13 2026). KTXS: project "described as" Abilene's largest single investment since Dyess AFB
Concerns / impacts
Grid electricity combined with on-site natural gas and battery storage (CNR)
Last verified
2026-10-18

Milestones

Figures are attributed in parentheses to the outlet or company that reported them. Where sources disagree, we show both.

  1. Mid-2024 vertical construction began (CNR)
  2. Feb 25 2025 Taylor County amended Lancium abatement, 80% for 10 yrs (per KTAB)
  3. Sep 9 2025 Taylor County Resolution 22-25 approved abatement agreements with Lancium and Abilene DC 1, 3–8 LLCs (term not stated in resolution)
  4. Sep 30 2025 first 2 buildings live (DCD)
  5. Mar 2026 2 GW expansion dropped (DCD). Completion dates differ: 8 buildings through Q1 2027 (Crusoe SVP via KTXS, Mar 5 2026)
  6. phase 2 complete by end-2026 (Crusoe, Mar 27 2026)
  7. buildings complete end-2026, closeout early 2027 (CNR, Aug 13 2026)
  8. TDLR 'Project Plaid' registrations at 615 FM 2404 (owner Data Center 3-8 Hold Co, LLC; Building 3 shell filed by Crusoe Energy Systems): Feb 13 2025 Building 3 shell (484,960 sq ft) and Mar 10 2025 Building 4 shell (479,721 sq ft)
  9. Apr 17 2025 Buildings 5–8 shells (~480,000 sq ft each)
  10. shells est. $292M each
  11. Mar 20–25 2025 Building 3 and 4 TIs and May 14 2025 Building 5–8 TIs (office and data hall build-outs, est. $384M each). Buildings 3–6 shell and TI filings show Inspection Complete
  12. 7–8 Review Complete (TDLR, found Oct 18 2026)

Linked power & water

Power

  • News report On-site gas and battery storage: Grid electricity combined with on-site natural gas and battery storage (CNR). mycnr.com (link unavailable: CNR article removed by the publisher; no archived copy found (checked Nov 9, 2026))

Power and water projects tied to this data center: on-site or dedicated generation, utility and grid capacity deals, substations, water supply, reclaimed water and wastewater permits. Each item is labeled by source type.

Land, jobs & economic impact

No land purchase, jobs or economic impact figure from a deed, agreement, filing or company release has been found for this project yet.

Related records

2026-08-13
News News report Taylor County · Stargate I / Crusoe Abilene AI Campus (Lancium Clean Campus)

CNR: DPR building current Abilene phase; buildings complete end-2026, closeout early 2027; up to 5,000 workers at peak.

Source: mycnr.com (link unavailable: CNR article removed by the publisher; no archived copy found (checked Nov 9, 2026))
2026-03-06
News News report Taylor County · Stargate I / Crusoe Abilene AI Campus (Lancium Clean Campus)

DCD: Oracle/OpenAI drop plans to expand the Abilene Stargate site to 2 GW.

Source: datacenterdynamics.com ↗
2026-03-05
News News report Taylor County · Stargate I / Crusoe Abilene AI Campus (Lancium Clean Campus)

KTXS: Crusoe SVP briefs Abilene leaders; ~9,000 craft workers on site daily; 8 buildings through Q1 2027.

Source: ktxs.com ↗
2025-09-09
Tax abatement Official record Taylor County · Stargate I / Crusoe Abilene AI Campus (Lancium Clean Campus)

Commissioners Court unanimously approves Resolution 22-25: abatement agreements with Lancium and Abilene DC 1, 3–8 LLCs (draft minutes; term not stated).

Source: taylorcotx.api.civicclerk.com ↗
2025-05-14
Building registration (TDLR) Official record Taylor County · Stargate I / Crusoe Abilene AI Campus (Lancium Clean Campus)

TDLR TABS: 'Project Plaid' Crusoe Building 5–8 tenant improvements, office and data hall build-outs, est. $384M each.

Source: tdlr.texas.gov ↗
2025-04-17
Building registration (TDLR) Official record Taylor County · Stargate I / Crusoe Abilene AI Campus (Lancium Clean Campus)

TDLR TABS: 'Project Plaid' Crusoe Buildings 5–8, ~480,000 sq ft data halls, est. $292M each; owner Data Center 3-8 Hold Co, LLC.

Source: tdlr.texas.gov ↗
2025-02-25
Tax abatement News report Taylor County · Stargate I / Crusoe Abilene AI Campus (Lancium Clean Campus)

KTAB: Taylor County commissioners amend Lancium abatement; 80% of property value abated for 10 years.

Source: finance.yahoo.com ↗
2025-02-13
Building registration (TDLR) Official record Taylor County · Stargate I / Crusoe Abilene AI Campus (Lancium Clean Campus)

TDLR TABS: 'Project Plaid' Crusoe Building 3, 484,960 sq ft single-story data center, est. $292M, 615 FM 2404; now Inspection Complete.

Source: tdlr.texas.gov ↗

Sources

Found an error? Email [email protected] with a source link.

Free

Get the free weekly digest for your county

Free weekly email every Friday for your first month, for 1 county you pick: new commissioners court actions, permits, filings and hearings, plus the week's top Texas changes. Every item links to its public source.

Same-day alerts come with Neighbor ($4/mo).