Home / Hood County / Project
Comanche Circle data center development
Sailfish
In short: Location: Comanche Circle area, Hood County, Texas. Status: On-site permit denied (appeal denied). Developer or parties: Sailfish. Size: 2,102 acres (county notice of conditional approval). Latest record (Oct 13, 2026): Court rejected Sailfish settlement 3-1 (nay Andrews; Samuelson absent) and unanimously denied the on-site permit appeal for Comanche Circle, Lion, and Panther (KERA; Star-Telegram; minutes not yet… Last verified Oct 13, 2026.
- Status
- On-site permit denied (appeal denied)
- Developer / parties
- Sailfish
- Location
- Comanche Circle area, Hood County
- Size
- 2,102 acres (county notice of conditional approval)
- Concerns / impacts
- Residents cited noise from an existing Bitcoin mine, water use (KERA, archived)
- Last verified
- 2026-10-13
Milestones
- Dec 3 2025 concept plan submitted
- Jan 13 2026 Commissioners Court conditionally approved the concept plan 4-1, Comm. Eagle voting no (Jan 13 minutes, official)
- KERA (archived) reports conditions on drainage, wastewater, landscape impact and power generation to be addressed "within 45 days". Tally conflict: Feb 10 minutes record "Post motion discussion by Comm. Eagle regarding he and Comm. Samuelson were the two 'no' votes when the first conditional approval was done" (official)
- tracker follows the Jan 13 tally
- Feb 10 2026 court added conditions 3-2 (nay Eagle, Samuelson), and a motion to amend regulations to allow moratoriums failed 2-3, so the moratorium item was pulled (minutes)
- Feb 10 2026 county issued revised notice of conditional approval
- status was "Approved (conditional)" until Jun 9 2026, when the court voted 3-1 to approve the concept plan without conditions, Comm. Samuelson voting no and Comm. Eagle absent, moving the project to site development plan review (KERA)
- Sep 8 2026 court tabled the item on the on-site permit status of Sailfish Projects Comanche Circle, Lion and Panther and set it for the Oct 13 2026 regular court after Comm. Eagle said it required notice as a public hearing under Development Permit Regulations 4.5(c)
- motion carried 4-0 (Sep 8 minutes, official)
- a published legal notice says the court received a Notice of Appeal under Sec. 4.5.C.3 on the on-site permit decisions for Sailfish Investors Acquisitions LLC (Comanche Circle, Project Lion, Project Panther) and set a hearing for Oct 13 2026 (legal notice)
- the official Oct 13 2026 Modified Public Agenda confirms the regular meeting at 9:00 a.m. in the Central Jury Room, Ralph H. Walton Jr. Justice Center, 1200 W. Pearl St., Granbury (official agenda)
- Oct 13 2026 Modified Public Agenda (official, Documents-on-Demand, created Oct 9) item 15: review and discuss proposal from Sailfish Investors regarding Projects Comanche Circle, Lion and Panther, take appropriate action if any
- item 16: public hearing to consider the appeal of Hood County's denial of Sailfish Investors' On-Site Permit submission for Projects Comanche Circle, Lion and Panther, take any appropriate action regarding the submissions (official agenda)
- Oct 13 2026 Commissioners Court (KERA; Star-Telegram): rejected Sailfish settlement proposal 3-1 (nay Andrews; Samuelson absent)
- settlement would have cut Hood County footprint from about 2,523 acres to about 1,375 acres with voluntary setbacks, cooling, light, and road commitments
- then unanimously denied Sailfish Investors' appeal of the on-site permit denials for Comanche Circle, Lion, and Panther
- Star-Telegram qquotes managing partner Ryan Hughes saying it looks like they are going to court
- official minutes not yet posted on the county portal as of evening Oct 13
- NRG withdrew its air permit application for the 1,200 MW Tolar Power Center that would have supplied Comanche Circle (NBC 5)
Linked power & water
Power
- News report Tolar Power Center (1,200 MW, proposed): Air permit application for the 1,200 MW Tolar Power Center that would have supplied Comanche Circle (NBC 5, as recorded). nbcdfw.com ↗
Land, jobs & economic impact
Related records
Court rejected Sailfish settlement 3-1 (nay Andrews; Samuelson absent) and unanimously denied the on-site permit appeal for Comanche Circle, Lion, and Panther (KERA; Star-Telegram; minutes not yet posted).
Source: kera.org ↗KERA: Hood County rejects Sailfish Comanche Circle settlement 3-1 and unanimously denies on-site permit appeal.
Source: kera.org ↗Star-Telegram: commissioners deny Sailfish settlement and permit appeal; Hughes says it looks like they are going to court.
Source: star-telegram.com ↗Minutes: court tables on-site permit item for Sailfish's Comanche Circle, Lion and Panther; sets it for Oct 13 regular court as public hearing; 4-0.
Source: hoodcountytx.documents-on-demand.com ↗Court votes 3-1 to approve Comanche Circle concept plan without conditions (nay Samuelson; Eagle absent), per KERA.
Source: kera.org ↗Minutes: Comanche Circle conditions modified 3-2; moratorium-enabling amendments fail 2-3; moratorium item pulled.
Source: hoodcountytx.documents-on-demand.com ↗Minutes: Commissioners Court conditionally approves Comanche Circle concept plan 4-1 (nay Comm. Eagle).
Source: hoodcountytx.documents-on-demand.com ↗Sources
- News report web.archive.org
- Official record hoodcountytx.documents-on-demand.com
- Official record hoodcountytx.documents-on-demand.com
- Official record hoodcountytx.documents-on-demand.com
- News report kera.org
- News report nbcdfw.com
- Official record hoodcountytx.documents-on-demand.com
- Official record hoodcountytx.documents-on-demand.com
- Official record hoodcountytx.documents-on-demand.com
- News report kera.org
- News report star-telegram.com
Free
Get the free weekly digest for your county
Free weekly email every Friday for your first month, for 1 county you pick: new commissioners court actions, permits, filings and hearings, plus the week's top Texas changes. Every item links to its public source.
Same-day alerts come with Neighbor ($4/mo).