Comanche Circle data center development

Sailfish

In short: Location: Comanche Circle area, Hood County, Texas. Status: On-site permit denied (appeal denied). Developer or parties: Sailfish. Size: 2,102 acres (county notice of conditional approval). Latest record (Oct 13, 2026): Court rejected Sailfish settlement 3-1 (nay Andrews; Samuelson absent) and unanimously denied the on-site permit appeal for Comanche Circle, Lion, and Panther (KERA; Star-Telegram; minutes not yet… Last verified Oct 13, 2026.

Status
On-site permit denied (appeal denied)
Developer / parties
Sailfish
Location
Comanche Circle area, Hood County
Size
2,102 acres (county notice of conditional approval)
Concerns / impacts
Residents cited noise from an existing Bitcoin mine, water use (KERA, archived)
Last verified
2026-10-13

Milestones

Figures are attributed in parentheses to the outlet or company that reported them. Where sources disagree, we show both.

  1. Dec 3 2025 concept plan submitted
  2. Jan 13 2026 Commissioners Court conditionally approved the concept plan 4-1, Comm. Eagle voting no (Jan 13 minutes, official)
  3. KERA (archived) reports conditions on drainage, wastewater, landscape impact and power generation to be addressed "within 45 days". Tally conflict: Feb 10 minutes record "Post motion discussion by Comm. Eagle regarding he and Comm. Samuelson were the two 'no' votes when the first conditional approval was done" (official)
  4. tracker follows the Jan 13 tally
  5. Feb 10 2026 court added conditions 3-2 (nay Eagle, Samuelson), and a motion to amend regulations to allow moratoriums failed 2-3, so the moratorium item was pulled (minutes)
  6. Feb 10 2026 county issued revised notice of conditional approval
  7. status was "Approved (conditional)" until Jun 9 2026, when the court voted 3-1 to approve the concept plan without conditions, Comm. Samuelson voting no and Comm. Eagle absent, moving the project to site development plan review (KERA)
  8. Sep 8 2026 court tabled the item on the on-site permit status of Sailfish Projects Comanche Circle, Lion and Panther and set it for the Oct 13 2026 regular court after Comm. Eagle said it required notice as a public hearing under Development Permit Regulations 4.5(c)
  9. motion carried 4-0 (Sep 8 minutes, official)
  10. a published legal notice says the court received a Notice of Appeal under Sec. 4.5.C.3 on the on-site permit decisions for Sailfish Investors Acquisitions LLC (Comanche Circle, Project Lion, Project Panther) and set a hearing for Oct 13 2026 (legal notice)
  11. the official Oct 13 2026 Modified Public Agenda confirms the regular meeting at 9:00 a.m. in the Central Jury Room, Ralph H. Walton Jr. Justice Center, 1200 W. Pearl St., Granbury (official agenda)
  12. Oct 13 2026 Modified Public Agenda (official, Documents-on-Demand, created Oct 9) item 15: review and discuss proposal from Sailfish Investors regarding Projects Comanche Circle, Lion and Panther, take appropriate action if any
  13. item 16: public hearing to consider the appeal of Hood County's denial of Sailfish Investors' On-Site Permit submission for Projects Comanche Circle, Lion and Panther, take any appropriate action regarding the submissions (official agenda)
  14. Oct 13 2026 Commissioners Court (KERA; Star-Telegram): rejected Sailfish settlement proposal 3-1 (nay Andrews; Samuelson absent)
  15. settlement would have cut Hood County footprint from about 2,523 acres to about 1,375 acres with voluntary setbacks, cooling, light, and road commitments
  16. then unanimously denied Sailfish Investors' appeal of the on-site permit denials for Comanche Circle, Lion, and Panther
  17. Star-Telegram qquotes managing partner Ryan Hughes saying it looks like they are going to court
  18. official minutes not yet posted on the county portal as of evening Oct 13
  19. NRG withdrew its air permit application for the 1,200 MW Tolar Power Center that would have supplied Comanche Circle (NBC 5)

Linked power & water

Power

  • News report Tolar Power Center (1,200 MW, proposed): Air permit application for the 1,200 MW Tolar Power Center that would have supplied Comanche Circle (NBC 5, as recorded). nbcdfw.com ↗

Power and water projects tied to this data center: on-site or dedicated generation, utility and grid capacity deals, substations, water supply, reclaimed water and wastewater permits. Each item is labeled by source type.

Land, jobs & economic impact

No land purchase, jobs or economic impact figure from a deed, agreement, filing or company release has been found for this project yet.

Related records

2026-10-13
Commissioners court News report Hood County · Comanche Circle data center development

Court rejected Sailfish settlement 3-1 (nay Andrews; Samuelson absent) and unanimously denied the on-site permit appeal for Comanche Circle, Lion, and Panther (KERA; Star-Telegram; minutes not yet posted).

Source: kera.org ↗
2026-10-13
News News report Hood County · Comanche Circle data center development

KERA: Hood County rejects Sailfish Comanche Circle settlement 3-1 and unanimously denies on-site permit appeal.

Source: kera.org ↗
2026-10-13
News News report Hood County · Comanche Circle data center development

Star-Telegram: commissioners deny Sailfish settlement and permit appeal; Hughes says it looks like they are going to court.

Source: star-telegram.com ↗
2026-09-08
Commissioners court Official record Hood County · Comanche Circle data center development

Minutes: court tables on-site permit item for Sailfish's Comanche Circle, Lion and Panther; sets it for Oct 13 regular court as public hearing; 4-0.

Source: hoodcountytx.documents-on-demand.com ↗
2026-06-09
Commissioners court News report Hood County · Comanche Circle data center development

Court votes 3-1 to approve Comanche Circle concept plan without conditions (nay Samuelson; Eagle absent), per KERA.

Source: kera.org ↗
2026-02-10
Commissioners court Official record Hood County · Comanche Circle data center development

Minutes: Comanche Circle conditions modified 3-2; moratorium-enabling amendments fail 2-3; moratorium item pulled.

Source: hoodcountytx.documents-on-demand.com ↗
2026-01-13
Commissioners court Official record Hood County · Comanche Circle data center development

Minutes: Commissioners Court conditionally approves Comanche Circle concept plan 4-1 (nay Comm. Eagle).

Source: hoodcountytx.documents-on-demand.com ↗

Sources

Found an error? Email [email protected] with a source link.