Home / Harris County / Project
Raeden inference data center (former bottling plant, Fidelity Street, Jacinto City)
Raeden (company president Jason Green, per ABC13 / North Channel Star); property owner IRGRA (per city manager, North Channel Star)
In short: Location: Jacinto City (former glass bottling plant on Fidelity Street), Harris County, Texas. Status: Proposed / in development (no formal proposal or submittals to the city as of mid-Sep 2026). Developer or parties: Raeden (company president Jason Green, per ABC13 / North Channel Star); property owner IRGRA (per city manager, North Channel Star). Size: About 50 MW (ABC13). Latest record (Sep 17, 2026): North Channel Star: Jacinto City has no formal Raeden submittals; city drafting specific use permit rules for data centers. Last verified Nov 16, 2026.
- Status
- Proposed / in development (no formal proposal or submittals to the city as of mid-Sep 2026)
- Developer / parties
- Raeden (company president Jason Green, per ABC13 / North Channel Star); property owner IRGRA (per city manager, North Channel Star)
- Location
- Jacinto City (former glass bottling plant on Fidelity Street), Harris County
- Size
- About 50 MW (ABC13)
- Concerns / impacts
- Residents and city leaders oppose; water, noise and power concerns; city seeks enforceable water limits and separate cooling-water meters (North Channel Star)
- Last verified
- 2026-11-16
Milestones
- Jul 2026 Jacinto City passed a resolution opposing data center construction (ABC13)
- Sep 11 2026 town hall called by city leaders, residents opposed (ABC13)
- Raeden said it would like to begin redevelopment as early as October 2026 (KPRC Click2Houston)
- city manager Lon Squyres said the city had not received a formal proposal, building plans or other submittals and was drafting a zoning ordinance requiring a specific use permit for data centers (North Channel Star, Sep 17 2026). Construction start not confirmed
Linked power & water
Water
- News report Closed-loop cooling (company statement): Raeden representative Jason Green repeatedly stated the data center would use a closed-loop cooling system; the city plans separate meters for cooling water (North Channel Star). northchannelstar.com ↗
Land, jobs & economic impact
Related records
North Channel Star: Jacinto City has no formal Raeden submittals; city drafting specific use permit rules for data centers.
Source: northchannelstar.com ↗ABC13: residents oppose Raeden's proposed 50 MW data center in a vacant bottling plant on Fidelity Street at a city town hall.
Source: abc13.com ↗Sources
- News report abc13.com
- News report click2houston.com
- News report northchannelstar.com