Home / Kaufman County / Project

Prometheus Hyperscale Kaufman County campus (FM 987)

Prometheus Hyperscale; Conduit Power (on-site gas and storage partner, per company)

Status
Proposed / in development
Developer / parties
Prometheus Hyperscale; Conduit Power (on-site gas and storage partner, per company)
Location
Between Talty and Post Oak Bend City (company via Greenville Chronicle); northeast side of FM 987 between the FM 987/FM 2578 intersection and CR 272 (Rose Hill SUD), Kaufman County
Size
About 500 acres; up to 200 MW of utility load in four buildings (company via Greenville Chronicle); concept plan shows about 320 acres developed on a 500+ acre property (Rose Hill SUD)
Last verified
2026-11-01

Milestones

Figures are attributed in parentheses to the outlet or company that reported them. Where sources disagree, we show both.

  1. Feb 2026 Kaufman County Development Services met the developer about a concept plan
  2. as of Aug 7 2026 no formal application to the county and no water service request to Rose Hill SUD, NTMWD or four neighboring providers (Rose Hill SUD notice)
  3. May 2026 company president Trevor Neilson announced the campus on LinkedIn (Greenville Chronicle, May 22 2026)

Linked power & water

Power

  • Company claim Behind-the-meter Jenbacher J620 gas engines; nearby Engie BESS: Behind-the-meter generation with Jenbacher J620 natural gas engines and a connection to a nearby Engie North America battery storage system; Conduit Power partner (company via Greenville Chronicle). greenvillechronicle.com ↗

Water

  • Official record No water service request on record: Rose Hill SUD: no water service request from Prometheus to Rose Hill SUD, NTMWD or four neighboring providers in records reviewed; NTMWD South Transmission Line is a separate project. rhsud.com ↗

Power and water projects tied to this data center: on-site or dedicated generation, utility and grid capacity deals, substations, water supply, reclaimed water and wastewater permits. Each item is labeled by source type.

Land, jobs & economic impact

No land purchase, jobs or economic impact figure from a deed, agreement, filing or company release has been found for this project yet.

Related records

2026-08-07
News News report Kaufman County · Prometheus Hyperscale Kaufman County campus (FM 987)

Rose Hill SUD notice: Prometheus concept plan ~320 of 500+ acres on FM 987; no formal county application or water service request found.

Source: rhsud.com ↗
2026-05-22
News News report Kaufman County · Prometheus Hyperscale Kaufman County campus (FM 987)

Greenville Chronicle: Prometheus Hyperscale plans ~500-acre, up to 200 MW campus between Talty and Post Oak Bend City (company LinkedIn post).

Source: greenvillechronicle.com ↗

Sources

Found an error? Email [email protected] with a source link.