Home / Hood County / Project

Project Patriot (Bilateral Energy digital infrastructure campus, former Knox Ranch property, Granbury)

Bilateral Energy (company site; named on the City of Granbury Project Patriot page)

In short: Location: Granbury (Knox Ranch property, per City of Granbury), Hood County, Texas. Status: Proposed / in development (concept plan received; no development application or site plan as of city updates). Developer or parties: Bilateral Energy (company site; named on the City of Granbury Project Patriot page). Size: Approximately 2,000 acres (company claim); MW not stated. Latest record (Nov 6, 2026): City of Granbury Project Patriot page (updated Nov 6): concept plan received; no development plans as of Oct 8; no data center approval or abatements. Last verified Nov 16, 2026.

Status
Proposed / in development (concept plan received; no development application or site plan as of city updates)
Developer / parties
Bilateral Energy (company site; named on the City of Granbury Project Patriot page)
Location
Granbury (Knox Ranch property, per City of Granbury), Hood County
Size
Approximately 2,000 acres (company claim); MW not stated
Concerns / impacts
Residents dispute the City's handling of the project (City rumor/truth page addresses claims of concealment and personal benefit)
Last verified
2026-11-16

Milestones

Figures are attributed in parentheses to the outlet or company that reported them. Where sources disagree, we show both.

  1. Jun 23 2026 Project Concept Plan document posted by the City
  2. the City says receipt of a Concept Plan vests the project under the rules in effect on that date
  3. as of Sep 9 2026 the City had not received a development application or approved a site plan
  4. as of Oct 8 2026 it had not received any development plans
  5. the City has not approved or permitted a data center and has not approved tax abatements or incentives
  6. annexation was requested by the private property owner
  7. Ordinance 26-14 (Apr 2026) set standards for data centers and power-generation facilities (City of Granbury Project Patriot page, last updated Nov 6 2026). Distinct from the county-level Sailfish Comanche Circle project (sailfish-hood)

Linked power & water

Power

  • Company claim On-site power generation (self-sufficient campus): Planned as a self-sufficient campus with on-site power generation designed to operate independently of the local grid; evaluating a future interconnection to deliver surplus power to the regional grid (company claim). No TCEQ permit opened this run. projectpatriotusa.com ↗

Power and water projects tied to this data center: on-site or dedicated generation, utility and grid capacity deals, substations, water supply, reclaimed water and wastewater permits. Each item is labeled by source type.

Land, jobs & economic impact

No land purchase, jobs or economic impact figure from a deed, agreement, filing or company release has been found for this project yet.

Related records

2026-11-06
City council News report Hood County · Project Patriot (Bilateral Energy digital infrastructure campus, former Knox Ranch property, Granbury)

City of Granbury Project Patriot page (updated Nov 6): concept plan received; no development plans as of Oct 8; no data center approval or abatements.

Source: granbury.org ↗

Sources

Found an error? Email [email protected] with a source link.