IREN Sweetwater 1 (part of 2 GW Sweetwater hub)

IREN

In short: Location: Sweetwater area (company: "Sweetwater TX"), Nolan County and Fisher County, Texas. Status: Under construction. Developer or parties: IREN. Size: 1.4 GW site; 300 MW gross targeted Q4 2027; hub 2 GW with Sweetwater 2. Latest record (Sep 8, 2026): IREN says its 2 GW Sweetwater hub was conditionally included as base load in ERCOT Batch Zero. Last verified Oct 3, 2026.

Status
Under construction
Developer / parties
IREN
Location
Sweetwater area (company: "Sweetwater TX"), Nolan County, Fisher County (Nolan / Fisher (conflicting reports))
Size
1.4 GW site; 300 MW gross targeted Q4 2027; hub 2 GW with Sweetwater 2
Last verified
2026-10-03

Milestones

Figures are attributed in parentheses to the outlet or company that reported them. Where sources disagree, we show both.

  1. May 1 2026 substation energized/connected to ERCOT
  2. Sep 8 2026 conditionally included as base load in ERCOT Batch Zero (IREN). County unresolved
  3. no official record names Sweetwater 1's county. Fisher: DCD
  4. Double Mountain Chronicle (Fisher County paper) calls Sweetwater 1 IREN's Fisher County project
  5. IREN runs a Fisher County community grants program (company)
  6. PUCT filing places an IREN 'Project Bull' 345-kV delivery point in Fisher County (official; does not name Sweetwater)
  7. Fisher County minutes (official): Aug 12 2024 information-only item on an IREN data center project
  8. Dec 9 2024 court unanimously designated reinvestment zones and approved tax abatement agreements for IE US Development Holdings 7 Inc. & IE US Hardware 1 Inc. ('Project Castle') and IE US Development Holdings 5 Inc. & IE US Hardware 1 Inc. ('Project Bull'), with an IREN representative listed on the agenda
  9. Feb 10 2025 FYI item 'Construction of the IREN project bull'. None of these county records names Sweetwater 1, so they do not settle the county. Nolan County minutes posted for 2023 through Sep 2026 show no IREN item (searched Oct 5 2026 via OCR). Nolan: Blockspace. IREN FY2026 10-K lists 'Sweetwater 1, Texas' without a county

Linked power & water

Power

  • Company claim Sweetwater 1 substation (ERCOT-connected): May 1 2026 substation energized and connected to ERCOT (IREN). globenewswire.com ↗

Power and water projects tied to this data center: on-site or dedicated generation, utility and grid capacity deals, substations, water supply, reclaimed water and wastewater permits. Each item is labeled by source type.

Land, jobs & economic impact

No land purchase, jobs or economic impact figure from a deed, agreement, filing or company release has been found for this project yet.

Related records

2026-09-08
Grid/ERCOT Company claim Nolan County · Fisher County · IREN Sweetwater 1 (part of 2 GW Sweetwater hub)

IREN says its 2 GW Sweetwater hub was conditionally included as base load in ERCOT Batch Zero.

Source: globenewswire.com ↗
2026-05-01
Grid/ERCOT Company claim Nolan County · Fisher County · IREN Sweetwater 1 (part of 2 GW Sweetwater hub)

IREN announces energization of Sweetwater 1 substation.

Source: globenewswire.com ↗

Sources

Found an error? Email [email protected] with a source link.

Free

Get the free weekly digest for your county

Free weekly email every Friday for your first month, for 1 county you pick: new commissioners court actions, permits, filings and hearings, plus the week's top Texas changes. Every item links to its public source.

Same-day alerts come with Neighbor ($4/mo).