Project Matador (HyperGrid campus)
Fermi America
In short: Location: Amarillo area, Carson County, Texas. Status: In development. Developer or parties: Fermi America. Size: 4 proposed AP1000 reactors under NRC review; reactors 'would provide 4 GWs' of baseload power and campus may include ~11 GW total generation and up to 30M sq ft of computing… Latest record (Nov 13, 2026): Alliance News: Financial Times reports Amazon is Fermi's unnamed 600 MW Matador customer; Fermi declined comment; Fermi and TensorWave ended their lease. Last verified Oct 15, 2026.
- Status
- In development
- Developer / parties
- Fermi America
- Location
- Amarillo area, Carson County
- Size
- 4 proposed AP1000 reactors under NRC review; reactors 'would provide 4 GWs' of baseload power and campus may include ~11 GW total generation and up to 30M sq ft of computing space (NRC, Federal Register); four AP1000s 'totalling 4.4 GWe' within a planned 17 GWe campus (NEI Magazine, citing Fermi); first Siemens Energy gas turbines arrived on site (Fermi, via CRO); subject to binding customer agreements, expected to ramp to about 17 GW (Fermi Oct 13 2026 release)
- Last verified
- 2026-10-15
Milestones
- Jun 17 2025 COL application initial submittal
- Sep 5 2025 NRC acceptance letter
- Mar 20 2026 NRC notice of intent to prepare EIS, scoping comments due Apr 20 2026 (Federal Register)
- Sep 28 2026 NAES selected to operate gas turbine fleet (CRO)
- nuclear construction slated to begin 2031 (NEI Magazine, Mar 17 2026)
- Oct 13 2026 Fermi announced AMD credit support for the phase-one 222 MW lease with TensorWave and a partnership framework for future expansion up to 650 MW gross (Fermi release via Nasdaq; company claim). Nov 12 2026 Fermi announced agreements with an undisclosed investment-grade hyperscaler for an initial 600 MW beginning in 2027 ($200M prepayment and $15M early construction agreements; long-term lease still under negotiation) and said on its earnings call the TensorWave lease will not move forward (company claims). Current NRC docket status not re-checked: nrc.gov blocked our fetchers
Linked power & water
Power
- Official record AP1000 nuclear units (NRC combined license review): Four proposed AP1000 reactors under NRC review would provide 4 GW of baseload power (Federal Register). govinfo.gov ↗
- Official record East Campus gas-fired power plant (TCEQ 183462): Mar 27 2026 TCEQ received Fermi's application for a new natural gas-fired plant on the East Campus to supply the on-site data center campus (TCEQ). tceq.texas.gov ↗
- Company claim Three GE Vernova 6B gas turbines delivered (Oct 2026): Three GE Vernova 6B gas turbines arrived at the Project Matador site; Fermi says they join a portfolio of owned generation assets for a planned 17 GW private grid (Fermi). fermiamerica.com ↗
Land, jobs & economic impact
Land
- Official record Mar 30, 2026 · Lease and contracts · 5,236 acres: Fermi's 10-K says it satisfied the conditions to commence a 99-year ground lease with the Texas Tech University System covering about 5,236 acres in Carson County, signed contracts to acquire adjacent acreage (expanded campus about 7,570 acres), and had acquired or was under contract for about 2,000 additional acres west and south of the primary campus. A separate 30-year groundwater lease covers about 2,542 acres in Carson County. Prices are not stated here. sec.gov ↗
Related records
Alliance News: Financial Times reports Amazon is Fermi's unnamed 600 MW Matador customer; Fermi declined comment; Fermi and TensorWave ended their lease.
Source: morningstar.com ↗Fermi: undisclosed investment-grade hyperscaler signed $200M prepayment and $15M early-construction agreements for 600 MW at Project Matador; lease not final (company).
Source: accessnewswire.com ↗Fermi: three GE Vernova 6B gas turbines arrived at Project Matador, part of its planned 17 GW private-grid energy and AI campus (company).
Source: fermiamerica.com ↗DCD: Fermi signed a credit support agreement with AMD for the first 222 MW data center at Project Matador; framework for up to 650 MW.
Source: datacenterdynamics.com ↗Fermi: AMD signed credit support for the 222 MW phase-one lease and a framework for up to 650 MW more; called a milestone toward financing (company claim).
Source: nasdaq.com ↗TCEQ received Fermi's application (183462) for a new gas-fired power plant on the Project Matador East Campus to supply its data center campus.
Source: tceq.texas.gov ↗Federal Register: NRC intends to prepare EIS for Fermi America's four-unit AP1000 COL application; scoping comments due Apr 20 2026.
Source: govinfo.gov ↗Sources
- Official record govinfo.gov
- News report constructionreviewonline.com
- News report neimagazine.com
- News report nasdaq.com
Free
Get the free weekly digest for your county
Free weekly email every Friday for your first month, for 1 county you pick: new commissioners court actions, permits, filings and hearings, plus the week's top Texas changes. Every item links to its public source.
Same-day alerts come with Neighbor ($4/mo).