In short: Location: Near Sulphur Springs, on the former Monticello Thermo Mine along State Highway 11 (CyrusOne), Hopkins County, Texas. Status: Proposed / in development (due diligence; land litigation pending). Developer or parties: CyrusOne (company page); prior developer MSB Global no longer involved (KLTV). Size: Phased campus that could ultimately include multiple data center buildings; final site plan not yet determined (company claim). MW not stated by CyrusOne. Investment: $5 billion to $10 billion in private capital investment if fully built (company claim, CyrusOne page); $2.6 billion investment cited at the Sep 24 2026… Latest record (Nov 16, 2026): CyrusOne page (checked Nov 16): phased campus near Sulphur Springs in due diligence; $5-10B if fully built; on-site gas generation (company claim). Last verified Nov 16, 2026.
- Status
- Proposed / in development (due diligence; land litigation pending)
- Developer / parties
- CyrusOne (company page); prior developer MSB Global no longer involved (KLTV)
- Location
- Near Sulphur Springs, on the former Monticello Thermo Mine along State Highway 11 (CyrusOne), Hopkins County
- Size
- Phased campus that could ultimately include multiple data center buildings; final site plan not yet determined (company claim). MW not stated by CyrusOne
- Investment
- $5 billion to $10 billion in private capital investment if fully built (company claim, CyrusOne page); $2.6 billion investment cited at the Sep 24 2026 community meeting (KLTV)
- Reported benefits
- 30 to 40 permanent jobs per data center building and over a thousand construction jobs (KLTV, from the community meeting); hundreds of construction jobs during multi-year development (company claim)
- Concerns / impacts
- Deed covenant litigation over on-site power generation; residents raised noise concerns (KLTV)
- Last verified
- 2026-11-16
Milestones
- Sep 24 2026 CyrusOne held a community meeting at the Hopkins County Civic Center
- prior developer MSB Global is no longer involved after legal battles over the land
- the former landowner is suing the City of Sulphur Springs and the former developer, alleging the deed bars power generation
- a judge has ruled the land cannot have power generation while the case awaits trial set for next year (KLTV). CyrusOne page (checked Nov 16 2026): project still in due diligence and planning, no final site plan (company claim)
Linked power & water
Power
- Company claim New on-site natural gas generation; later transmission interconnection: Campus to be powered at startup by new on-site natural gas generation CyrusOne expects to be owned, operated and built by a leading US power company, later interconnecting with nearby transmission (CyrusOne). A court has barred power generation on the land pending trial (KLTV). cyrusone.com ↗
Water
- News report About 1,000 gallons of water a day per building: Each building would use around a thousand gallons of water a day (KLTV, from the CyrusOne community meeting). kltv.com ↗
Land, jobs & economic impact
Related records
CyrusOne page (checked Nov 16): phased campus near Sulphur Springs in due diligence; $5-10B if fully built; on-site gas generation (company claim).
Source: cyrusone.com ↗KLTV: CyrusOne community meeting on campus at former Thermo mine; $2.6B, 30-40 jobs per building; land litigation bars power generation pending trial.
Source: kltv.com ↗Sources
- Company claim cyrusone.com
- News report kltv.com
Free
Get the free weekly digest for your county
Free weekly email every Friday for your first month, for 1 county you pick: new commissioners court actions, permits, filings and hearings, plus the week's top Texas changes. Every item links to its public source.
Same-day alerts come with Neighbor ($4/mo).