Home / Somervell County / Project

Amazon Data Services large load at Comanche Peak nuclear plant (net metering application)

Amazon Data Services, Inc. (large-load customer); Comanche Peak Power Company LLC (generation applicant) (PUC Docket 59399 / ERCOT study)

Status
Proposed / in development (PUC net-metering approval pending)
Developer / parties
Amazon Data Services, Inc. (large-load customer); Comanche Peak Power Company LLC (generation applicant) (PUC Docket 59399 / ERCOT study)
Location
Not stated in the sources opened (Somervell County), Somervell County
Size
New 1,200 MW large load netted with the ~2,400 MW Comanche Peak nuclear plant; first 100 MW energized around Oct 2027 and all 1,200 MW around Oct 2031, per the energization schedule Amazon submitted to ERCOT (ERCOT study report, PUC Docket 59399)
Investment
Amazon is building a $5 billion data center project near the plant (per Utility Dive, Aug 10 2026; not stated in the PUC filing)
Concerns / impacts
PowerGrabTX reports a United Cooperative Services member-owner filed a public comment Nov 1 2026 objecting on transmission-impact and ratepayer-cost grounds (news; comment not opened). ERCOT's filing says the Amazon load may still be curtailed in emergencies and describes proposed conditions on curtailment (official)
Last verified
2026-11-03

Milestones

Figures are attributed in parentheses to the outlet or company that reported them. Where sources disagree, we show both.

  1. Feb 19 2026 Comanche Peak Power Company filed an application with the PUC for approval of a net metering arrangement with a new 1,200 MW large load (official, ERCOT filing in Docket 59399)
  2. May 19 2026 application amended to name Amazon Data Services, Inc. as the large-load customer, located in Somervell County (official)
  3. Jun 15 2026 ERCOT filed notice that it had the information needed to begin its study (official)
  4. Oct 13 2026 ERCOT filed its study results and recommendations with the PUC (Item 53, Docket 59399; official)
  5. Utility Dive reported Aug 10 2026 that Vistra and Amazon have a 20-year power purchase agreement for 1.2 GW from the plant with deliveries from 2027 (news, citing a Vistra earnings call)
  6. PowerGrabTX reported Nov 2 2026 that PUC staff filed Oct 30 recommending approval subject to ERCOT's conditions, that the PUC canceled the hearing and is deciding on written filings, and that a vote by the commission is the next step (news; the staff filing itself was not opened)

Linked power & water

Power

  • Official record Comanche Peak nuclear plant (~2,400 MW) netted with the Amazon load: ERCOT's study says the Amazon load will sit behind the same ERCOT settlement meter facilities as Comanche Peak and be netted with it; the area is dually certificated to United Cooperative Services and Texas-New Mexico Power (PUC Docket 59399, Item 53). interchange.puc.texas.gov ↗

Power and water projects tied to this data center: on-site or dedicated generation, utility and grid capacity deals, substations, water supply, reclaimed water and wastewater permits. Each item is labeled by source type.

Land, jobs & economic impact

No land purchase, jobs or economic impact figure from a deed, agreement, filing or company release has been found for this project yet.

Related records

2026-10-30
Grid/ERCOT News report Somervell County · Amazon Data Services large load at Comanche Peak nuclear plant (net metering application)

PowerGrabTX: PUC staff filed Oct 30 in Docket 59399 recommending approval subject to ERCOT's conditions; decision on written filings, no hearing (staff filing not opened).

Source: powergrabtx.com ↗
2026-10-13
Grid/ERCOT Official record Somervell County · Amazon Data Services large load at Comanche Peak nuclear plant (net metering application)

ERCOT filed its study of the Comanche Peak Power Company and Amazon net metering arrangement (new 1,200 MW load; PUC Docket 59399, Item 53); report proposes conditions including emergency curtailment.

Source: interchange.puc.texas.gov ↗
2026-08-10
News News report Somervell County · Amazon Data Services large load at Comanche Peak nuclear plant (net metering application)

Utility Dive: Vistra executives say the 1.2 GW Amazon deal at Comanche Peak is not expected to be affected by the Texas pause; Amazon is building a $5B data center near the plant.

Source: utilitydive.com ↗

Sources

Found an error? Email [email protected] with a source link.

Free

Get the free weekly digest for your county

Free weekly email every Friday for your first month, for 1 county you pick: new commissioners court actions, permits, filings and hearings, plus the week's top Texas changes. Every item links to its public source.

Same-day alerts come with Neighbor ($4/mo).