Texas Data Center Watch tracks one data center project in Wharton County: Project Eagle in Boling, from Amazon Data Services. State building registrations (TDLR TABS) list seven data center buildings of 189,060 sq ft each, at an estimated $300M apiece:

  • Building A, registered June 25, 2026: Aug. 1, 2026 start, Jan. 1, 2027 completion (TDLR A).
  • Buildings E, F, G, H, J and K, registered Aug. 5, 2026: Sept. 1, 2026 start, Sept. 1, 2027 completion (E; F; G; H; J; K).

An auxiliary water building (4,067 sq ft, $2M) was registered Aug. 4, 2026 under the TDLR project name "Project Eagle Building M" (facility "Auxiliary Water Building," 248 Eaglewod Rd, Boling) (TDLR). It is not the same record as Horizon Junction Building M in Floydada (TABS2026027106), which happens to list the same size and cost (Horizon Junction Building M).

On Sept. 8, 2026, the Coastal Bend Groundwater Conservation District issued groundwater permits for restrooms, construction and fire protection, not cooling (Houston Chronicle via GovTech, which also describes a nearly 3,000-acre, $10B campus with 13 data center buildings) (GovTech).

Note: "registered" means a state accessibility (TDLR) building registration, not an environmental permit.

Tracked projects

Project Developer Status Capacity / size Investment Key dates Sources
Project Eagle (Buildings A–H, J, K; auxiliary Buildings L, M, N), Boling Amazon Data Services, Inc. Registered (TDLR) 10 data center buildings × 189,060 sq ft (TDLR TABS) Est. $300M per building (TDLR TABS) Jun 25 2026 Building A registered (status: Review Complete · start Aug 1 2026, completion Jan 1 2027) · Aug 5 2026 Buildings E, F, G, H, J, K registered (Project Registered · start Sep 1 2026, completion Sep 1 2027) · Aug 4 2026 auxiliary water building registered under the TDLR project name "Project Eagle Building M" (facility "Auxiliary Water Building" · 248 Eaglewod Rd [sic], Boling, Wharton County · owner Amazon Data Services, Inc. · 4,067 sq ft · $2M · start Aug 1 2026, completion Jul 1 2027) (TDLR, re-checked Oct 5 2026) · not the same record as Horizon Junction Building M (TABS2026027106, Floydada), which has the same size and cost · Sep 8 2026 Coastal Bend Groundwater Conservation District issued groundwater permits for restrooms, construction and fire protection, not cooling (per Houston Chronicle via GovTech, which describes a nearly 3,000-acre, $10B campus with 13 data center buildings) · Jun 25 2026 Buildings B, C and D also registered at 258, 240 and 244 Eaglewood Rd (new data center buildings, 189,060 sq ft and est. $300M each · start Aug 1 2026 · completion Aug 1 2027 for B and Jan 1 2027 for C and D · status Review Complete · owner Amazon Data Services, Inc.) (TDLR, found Oct 18 2026) · Oct 14 2026 auxiliary Building L (213 Eaglewood Dr · new 31,739 sq ft · est. $16M · start Nov 1 2026, completion Sep 1 2027) and Building N (200 Eaglewood Rd · 1,575 sq ft · est. $1.6M · start Nov 1 2026, completion Nov 1 2027) registered · owner Amazon Data Services, Inc. · Project Registered · uses not stated beyond auxiliary (TDLR, found Oct 19 2026) TDLR TABS 1 · TDLR TABS 2 · TDLR TABS 3 · TDLR TABS 4 · TDLR TABS 5 · TDLR TABS 6 · TDLR TABS 7 · TDLR TABS 8 · DCD · GovTech (Houston Chronicle) · TDLR TABS 9 · TDLR TABS 10 · TDLR TABS 11 · TDLR TABS 12 · TDLR TABS 13

Sources for each project are linked in the table. Figures labeled "company" come from the developer.

Record timeline

Date Type What happened Source
Oct 14, 2026 Building registration (TDLR) TDLR TABS: Amazon 'Project Eagle' auxiliary Building L (31,739 sq ft, $16M) and Building N (1,575 sq ft, $1.6M), Boling. TDLR TABS
Oct 2, 2026 News Houston Chronicle (via GovTech): groundwater district issued Amazon permits Sep 8 for restrooms, construction, fire protection; cooling water not included. GovTech (Houston Chronicle)
Aug 5, 2026 Building registration (TDLR) TDLR TABS: Amazon 'Project Eagle' Buildings E, F, G, H, J, K registered, $300M each, Boling. TDLR TABS
Jun 25, 2026 Building registration (TDLR) TDLR TABS: Amazon 'Project Eagle – Building A', 189,060 sq ft, $300M, Boling. TDLR TABS
Jun 25, 2026 Building registration (TDLR) TDLR TABS: Amazon 'Project Eagle' Buildings B, C, D registered, 189,060 sq ft and $300M each, Eaglewood Rd, Boling. TDLR TABS

What's next

These dates come from the tracker. Texas Data Center Watch has no recorded upcoming Wharton County hearings or votes on data centers.

  • Jan. 1, 2027: Scheduled completion of Project Eagle Building A, per its TDLR registration (TDLR).
  • Sept. 1, 2027: Scheduled completion of Buildings E, F, G, H, J and K, per their TDLR registrations (TDLR E; TDLR K).
  • Statewide permit pause: Under the Governor's Sept. 21 order halting permits sought by data centers (Governor's office), TCEQ sent its Oct. 19 compliance letter: it says permits for infrastructure directly supporting data centers are paused, pending applications are being screened, and claimed authorizations are suspended where possible (TCEQ letter). The Texas Tribune reported Oct. 20 that TCEQ says stormwater permits flagged by Public Citizen were suspended (Texas Tribune). On Oct. 21 TCEQ posted that its STEERS e-filing system for automatic authorizations is temporarily shut down so staff can check whether applications relate to data centers (TCEQ STEERS notice); the Texas Tribune reports a spokesman said applications must be physically provided (Texas Tribune, Oct. 21). The tracker doesn't show whether any project in Wharton County has a pending TCEQ permit.

Frequently asked questions

What data center projects are tracked in Wharton County, Texas? One: Project Eagle (Buildings A–H, J, K; auxiliary Buildings L, M, N) in Boling, listed as registered (TDLR).

What is Amazon building in Boling? A data center campus called Project Eagle. State registrations list seven data center buildings of 189,060 sq ft each, at an estimated $300M apiece (TDLR A; TDLR E; TDLR K).

When will Project Eagle be finished? Building A lists a Jan. 1, 2027 completion (TDLR). The other six data center buildings list Sept. 1, 2027 (TDLR E).

Is Project Eagle's "Building M" the same as Horizon Junction's Building M? No. Eagle's auxiliary water building is TABS2026026969 in Boling, Wharton County (TDLR). Horizon Junction Building M is TABS2026027106 in Floydada, Floyd County (TDLR). Both list 4,067 sq ft and $2M.


Get alerts for Wharton County

  • Free: Add Wharton County to your free Community weekly digest (1 county).
  • $4/mo or $36/yr: Neighbor sends same-day alerts when new Wharton County agenda items, TCEQ filings, or abatement applications appear. It also includes comment-deadline reminders. It's free on request if cost is a barrier.

Free Friday digest: Get alerts for this county (one county, free for your first month). Same-day alerts from $4/mo on Pricing.

Texas Data Center Watch is independent. No paid placement, and paying subscribers never change what this page says. See an error or a missing project? Tell us at [email protected].

Free

Get the free weekly digest for your county

Free weekly email every Friday for your first month, for 1 county you pick: new commissioners court actions, permits, filings and hearings, plus the week's top Texas changes. Every item links to its public source.

Same-day alerts come with Neighbor ($4/mo).