Data Center Projects in Dallas County, Texas

Last verified: October 27, 2026 · 11 tracked projects · 22 tracked records

Overview

Texas Data Center Watch tracks 11 data center projects in Dallas County, including the STACK DFW02 campus on Belt Line Road in Lancaster. It is listed as Registered (TDLR).

State building registrations (TDLR TABS) list three two-story office and data center buildings:

  • DFW02A, 1000 E Beltline Rd: 360,028 sq ft, est. $79.7M; registered Jan. 30, 2025; start May 21, 2025, completion Mar. 1, 2027 (TDLR).
  • DFW02A-P2, 1100 E Beltline Rd: 360,044 sq ft, est. $202.2M; registered Dec. 17, 2025; start Jan. 30, 2026, completion Mar. 1, 2028 (TDLR).
  • DFW02B, 1130 E. Belt Line Rd: 360,044 sq ft, est. $540M; registered Oct. 5, 2026; start Mar. 1, 2027, completion Dec. 14, 2028 (TDLR).

The DFW02A filings carry STACK in their project names (owner SI DFW02A, LLC). The DFW02B filing doesn't name STACK; it lists owner SI DFW02CAMPUS LLC with the same Denver owner address, owner contact and design firm as the STACK-titled filings (TDLR DFW02B). STACK's own DFW02 campus brochure (2024) describes a 193-acre Lancaster campus with 312 MW of critical capacity, expandable to 504 MW, and its site plan labels a 54MW "DFW02B" building (STACK brochure). These are company figures. No official record Texas Data Center Watch has opened names SI DFW02CAMPUS LLC as a STACK entity, so the link between the DFW02B filing and STACK rests on the matching building name in STACK's brochure and the shared TDLR owner details.

Added since the Oct. 16 page update:

  • Schlachter hyperscale data center, Wilmer (TCEQ 'Project Longhorn'), Wilmer (area bounded by Belt Line Rd, Mason Rd, Ferris Rd and Lavender/Van Rd): listed as proposed (TCEQ air permit pending). Developer, per the tracker: Schlachter Realty, Ltd. (TCEQ applicant; the plain-language summary spells it 'Schlacter') (TCEQ 1 · TCEQ 2).
  • QTS DFW2 campus (DC2–DC7), Wilmer/Lancaster, Wilmer and Lancaster (Mason Rd, W Beltline Rd, Sunrise Rd, per TDLR): listed as registered (TDLR). Developer, per the tracker: QTS (TDLR owner QTS Dallas I, LLC) (TDLR TABS 1 · TDLR TABS 2 · TDLR TABS 3 · TDLR TABS 4 · TDLR TABS 5 · TDLR TABS 6 · TDLR TABS 7).
  • Stream Data Centers Wilmer (DFWC1 and Project Fir), Wilmer (930 N Sunrise Rd and 300 S Sunrise Rd, per TDLR): listed as registered (TDLR). Developer, per the tracker: Stream Data Centers (TDLR owners SDC DFWC, LP and SDC DFW VIII, L.P.) (TDLR TABS 1 · TDLR TABS 2).
  • Digital Realty Garland campus (DFW37, DFW39, DFW40, DFW45), Garland (Ferris Road and Holford Road, per TDLR): listed as existing campus; new buildings and fit-outs registered (TDLR). Developer, per the tracker: Digital Realty (TDLR owners Digital Realty, Digital Garland 2B, L.P., Digital Garland 2C, L.P.) (TDLR TABS 1 · TDLR TABS 2 · TDLR TABS 3 · TDLR TABS 4 · TDLR TABS 5 · TDLR TABS 6).
  • DA12 data center (1550 W Mockingbird Lane), Dallas (1550 West Mockingbird Lane, per TDLR): listed as registered (TDLR). Developer, per the tracker: Owner listed as 'DA12' (TDLR); operator not named in the filing (TDLR TABS 1 · TDLR TABS 2).
  • DA11 data center buildout (1990 N Stemmons Fwy), Dallas (1990 N Stemmons Fwy, per TDLR): listed as existing building; buildout registered (TDLR). Developer, per the tracker: Owner listed as an individual (TDLR); operator not named in the filing (TDLR TABS).
  • CoreSite DA1 (Irving), Irving (2701 E. Grauwyler, per TDLR): listed as registered (TDLR). Developer, per the tracker: CoreSite (TDLR owners Cantex Grauwyler LLC & CoreSite Real Estate IRV LLC) (TDLR TABS).
  • Edged Dallas DFW1-2 (Irving), Irving (501 N. Wildwood Dr, per TDLR): listed as registered (TDLR). Developer, per the tracker: Edged (TDLR owner Edged Dallas LLC) (TDLR TABS).
  • Skybox Lancaster 1, Lancaster (2401 South Dallas Ave., per TDLR): listed as registered (TDLR). Developer, per the tracker: Skybox Datacenters (per TDLR project name); TDLR owner Lancaster Data Center Campus, LP (TDLR TABS).
  • AREP Powerhouse Las Colinas, Irving (111 Customer Way, per TDLR): listed as registered (TDLR). Developer, per the tracker: American Real Estate Partners (TDLR owner) (TDLR TABS).

Note: "registered" means a state accessibility (TDLR) building registration, not an environmental permit or local approval.

Tracked projects

Project Developer Status Capacity / size Investment Key dates Sources
STACK DFW02 Lancaster data center campus (DFW02A, DFW02A-P2, DFW02B), Lancaster STACK Infrastructure (per TDLR project names "STACK - DFW02A" and "STACK - DFW02A-P2", and STACK's DFW02 campus brochure, whose site plan labels a DFW02B building); owner entities SI DFW02A, LLC and SI DFW02CAMPUS LLC (TDLR) Registered (TDLR) Three two-story office and data center buildings: DFW02A 360,028 sq ft; DFW02A-P2 360,044 sq ft; DFW02B 360,044 sq ft (TDLR). STACK's brochure describes a 193-acre DFW02 campus with 312 MW critical capacity expandable to 504 MW; its site plan shows DFW02A at 96MW and DFW02B, C, D and E at 54MW each (company) TDLR estimated costs: DFW02A $79.7M; DFW02A-P2 $202.2M; DFW02B $540M Jan 30 2025 DFW02A registered at 1000 E Beltline Rd (start May 21 2025, completion Mar 1 2027) · Dec 17 2025 DFW02A-P2 registered at 1100 E Beltline Rd (start Jan 30 2026, completion Mar 1 2028) · Oct 5 2026 DFW02B registered at 1130 E. Belt Line Rd (start Mar 1 2027, completion Dec 14 2028) (all TDLR, status Project Registered). The DFW02B filing does not name STACK · it lists owner SI DFW02CAMPUS LLC with the same Denver owner address, owner contact and design firm (Corgan) as the STACK-titled DFW02A filings. STACK's DFW02 brochure (uploaded Oct 2024) labels a 54MW "DFW02B" building on its Lancaster campus site plan (company). No opened official record names SI DFW02CAMPUS LLC as a STACK entity, so linking this filing to STACK rests on the matching building name in STACK's brochure and the shared TDLR owner details TDLR TABS 1 · TDLR TABS 2 · TDLR TABS 3 · STACK brochure
Schlachter hyperscale data center, Wilmer (TCEQ 'Project Longhorn'), Wilmer (area bounded by Belt Line Rd, Mason Rd, Ferris Rd and Lavender/Van Rd) Schlachter Realty, Ltd. (TCEQ applicant; the plain-language summary spells it 'Schlacter') Proposed (TCEQ air permit pending) Hyperscale data center with 891 Caterpillar 3516E emergency generators rated 3,000 kW standby each (TCEQ) Not recorded Jun 19 2026 TCEQ received application for permit 184454 and nonattainment permit N334, listed on TCEQ's pending permits page as 'Project Longhorn' (TCEQ). No developer or tenant named in the filing TCEQ 1 · TCEQ 2
QTS DFW2 campus (DC2–DC7), Wilmer/Lancaster, Wilmer and Lancaster (Mason Rd, W Beltline Rd, Sunrise Rd, per TDLR) QTS (TDLR owner QTS Dallas I, LLC) Registered (TDLR) Two-story data center buildings: DC2 ~470,000 sq ft and DC3 ~560,000 sq ft (303 Mason Rd); DC4 413,726 sq ft (794 W Beltline Rd); DC5 and DC6 363,500 sq ft each (421 Mason Rd); DC7 363,500 sq ft (1341 Sunrise Rd, Lancaster) (TDLR) TDLR est. costs as filed: DC2 $300M; DC3 $350M; DC4 $175M; DC5, DC6 and DC7 $290M each Apr 10 2025 DC2 and DC3 registered (completions Jun 1 2026 and Jan 1 2027) · Jun 17 2025 DC4 (completion May 1 2027) · Feb 20 2026 DC5 and DC6 (completion Sep 1 2027) · Apr 6 2026 DC7, re-filed Sep 22 2026 (the April filing's square-footage field reads 3,635,000 while its scope says 363,500 · completion Dec 1 2027) · all Project Registered (TDLR) TDLR TABS 1 · TDLR TABS 2 · TDLR TABS 3 · TDLR TABS 4 · TDLR TABS 5 · TDLR TABS 6 · TDLR TABS 7
Stream Data Centers Wilmer (DFWC1 and Project Fir), Wilmer (930 N Sunrise Rd and 300 S Sunrise Rd, per TDLR) Stream Data Centers (TDLR owners SDC DFWC, LP and SDC DFW VIII, L.P.) Registered (TDLR) DFWC1: new 2-story 48 MW, 360,750 sq ft data center, substation and campus entrance; Project Fir: 85,625 sq ft data center core and shell next to an existing data center (TDLR) DFWC1 est. $300M; Project Fir est. $167.3M (TDLR, as filed) Sep 21 2025 'Stream Data Centers - DFWC1' registered (start Apr 1 2026, completion Oct 27 2027 · Review Complete) · Oct 22 2025 'Project Fir' (Stream Wilmer FIR) registered as an addition next to an existing data center (completion Dec 1 2027 · Project Registered) (TDLR) TDLR TABS 1 · TDLR TABS 2
Digital Realty Garland campus (DFW37, DFW39, DFW40, DFW45), Garland (Ferris Road and Holford Road, per TDLR) Digital Realty (TDLR owners Digital Realty, Digital Garland 2B, L.P., Digital Garland 2C, L.P.) Existing campus; new buildings and fit-outs registered (TDLR) DFW40: six 8 MW suites (48 MW) in a 280,000 sq ft building, plus four 8 MW suites (32 MW) filed Mar 2026; DFW45: ~672,000 sq ft building with ten 8 MW suites (80 MW); DFW37: 110,916 sq ft fit-outs of an existing 2-story facility; DFW39: one suite fit-out (TDLR) TDLR est. costs as filed: DFW40 $75M (2025) and $140M (2026); DFW45 $300M; DFW37 fit-outs $136M and $60M; DFW39 suite $74.6M Mar 6 2025 DFW40 (48 MW) registered at 1512 Ferris Road (Review Complete) · Sep 10 2025 DFW37 Suite 105/205 fit-out · Dec 11 2025 DFW37 Suite 110/210 fit-out · Mar 5 2026 DFW40 suites 200/100/205/105 (32 MW) · Apr 20 2026 'Project Gold Phase 2 - DFW 39' suite at 805 Holford Road · Sep 8 2026 DFW45 at 1602 Ferris Road (completion Jan 1 2029) (TDLR) TDLR TABS 1 · TDLR TABS 2 · TDLR TABS 3 · TDLR TABS 4 · TDLR TABS 5 · TDLR TABS 6
DA12 data center (1550 W Mockingbird Lane), Dallas (1550 West Mockingbird Lane, per TDLR) Owner listed as 'DA12' (TDLR); operator not named in the filing Registered (TDLR) New four-story 372,517 sq ft data center; fit-out of 158,293 sq ft on floors 1–2 (TDLR) DA12-1 est. $542.8M; DA12-2 fit-out est. $293.7M (TDLR, as filed) Nov 19 2025 'DA12-1' registered (start Feb 19 2026, completion Oct 12 2027) · Nov 21 2025 'DA12-2' fit-out registered (Sep 29 2027–Mar 30 2028) · both Review Complete (TDLR) TDLR TABS 1 · TDLR TABS 2
DA11 data center buildout (1990 N Stemmons Fwy), Dallas (1990 N Stemmons Fwy, per TDLR) Owner listed as an individual (TDLR); operator not named in the filing Existing building; buildout registered (TDLR) 95,490 sq ft buildout across three floors of an existing 4-story data center (TDLR) Est. $108.45M (TDLR, as filed) Jun 17 2025 'DA11-4' registered (start Aug 29 2025, completion Aug 28 2026 · Review Complete) (TDLR) TDLR TABS
CoreSite DA1 (Irving), Irving (2701 E. Grauwyler, per TDLR) CoreSite (TDLR owners Cantex Grauwyler LLC & CoreSite Real Estate IRV LLC) Registered (TDLR) Two-story 230,000 sq ft data center base building (TDLR) Est. $200M (TDLR, as filed) Aug 31 2026 'CORESITE DA1' registered (start Jan 4 2027, completion Dec 31 2028 · Project Registered) (TDLR) TDLR TABS
Edged Dallas DFW1-2 (Irving), Irving (501 N. Wildwood Dr, per TDLR) Edged (TDLR owner Edged Dallas LLC) Registered (TDLR) 2-story tilt-wall data center, 257,874 sq ft (TDLR) Est. $177.8M (TDLR, as filed) Apr 20 2026 'Edged Dallas' DFW1-2 registered (start Jul 16 2026, completion Mar 27 2028 · Review Complete) (TDLR) TDLR TABS
Skybox Lancaster 1, Lancaster (2401 South Dallas Ave., per TDLR) Skybox Datacenters (per TDLR project name); TDLR owner Lancaster Data Center Campus, LP Registered (TDLR) Interior improvements to an existing 270,900 sq ft data center shell (TDLR) Est. $214.3M (TDLR, as filed) Jan 27 2025 'Skybox - Lancaster 1 Initial Improvements' registered (start Mar 1 2025, completion May 1 2026 · Project Registered) (TDLR) TDLR TABS
AREP Powerhouse Las Colinas, Irving (111 Customer Way, per TDLR) American Real Estate Partners (TDLR owner) Registered (TDLR) 2-story core and shell data center, 300,000 sq ft, 65 MW total load (TDLR) Est. $47M (TDLR, as filed) Mar 11 2025 'AREP Powerhouse Las Colinas' registered (start Sep 23 2025, completion Aug 14 2026 · Review Complete) (TDLR) TDLR TABS

Sources for each project are linked in the table. Figures labeled "company" come from the developer.

Record timeline

Date Type What happened Source
Oct 27, 2026 City council Coppell council agenda Oct 27: ordinance to require special use permits for data centers and crypto mining in Light Industrial zoning. Coppell agenda
Oct 6, 2026 TCEQ permit Public Citizen: permit-by-rule for 'Edged Energy NFL' in Irving reached engineer initial review Oct 6 (404 Media: filed for expedited review Oct 6). Public Citizen
Oct 5, 2026 Building registration (TDLR) TDLR TABS: 'DFW02B', two-story office and data center, 360,044 sq ft, est. $540M, 1130 E. Belt Line Rd, Lancaster; owner SI DFW02CAMPUS LLC. TDLR TABS
Sep 8, 2026 Building registration (TDLR) TDLR TABS: DFW45, ~672,000 sq ft data center with ten 8 MW suites (80 MW), est. $300M, 1602 Ferris Rd; owner Digital Garland 2C, L.P. TDLR TABS
Aug 31, 2026 Building registration (TDLR) TDLR TABS: 'CORESITE DA1', new two-story 230,000 sq ft data center base building, est. $200M, 2701 E. Grauwyler, Irving. TDLR TABS
Jun 19, 2026 TCEQ permit TCEQ received Schlachter Realty's application (184454/N334) for a Wilmer hyperscale data center with 891 emergency generators, listed as 'Project Longhorn'. TCEQ
Apr 20, 2026 Building registration (TDLR) TDLR TABS: 'Edged Dallas' DFW1-2, 2-story 257,874 sq ft data center, est. $177.8M, 501 N. Wildwood Dr, Irving. TDLR TABS
Apr 6, 2026 Building registration (TDLR) TDLR TABS: 'QTS DFW2-DC7', 363,500 sq ft two-story building, est. $290M, 1341 Sunrise Rd, Lancaster; re-filed Sep 22 2026. TDLR TABS
Mar 5, 2026 Building registration (TDLR) TDLR TABS: DFW40 data hall suites, four 8 MW suites (32 MW IT), est. $140M; owner Digital Garland 2B, L.P. TDLR TABS
Feb 20, 2026 Building registration (TDLR) TDLR TABS: 'QTS DFW2-DC5' and DC6, 363,500 sq ft two-story buildings, est. $290M each, 421 Mason Rd, Wilmer. TDLR TABS
Dec 17, 2025 Building registration (TDLR) TDLR TABS: 'STACK - DFW02A-P2', 360,044 sq ft data center building, est. $202.2M, 1100 E Beltline Rd, Lancaster; owner SI DFW02A, LLC. TDLR TABS
Nov 19, 2025 Building registration (TDLR) TDLR TABS: 'DA12-1', new four-story 372,517 sq ft data center, est. $542.8M, 1550 W Mockingbird Ln, Dallas; fit-out 'DA12-2' filed Nov 21. TDLR TABS
Oct 22, 2025 Building registration (TDLR) TDLR TABS: 'Project Fir', 85,625 sq ft data center core and shell next to an existing data center, est. $167.3M, 300 S Sunrise Rd, Wilmer. TDLR TABS
Sep 21, 2025 Building registration (TDLR) TDLR TABS: 'Stream Data Centers - DFWC1', new 2-story 48 MW 360,750 sq ft data center plus substation, est. $300M, 930 N Sunrise Rd, Wilmer. TDLR TABS
Sep 10, 2025 Building registration (TDLR) TDLR TABS: 'Digital Realty DFW37 Suite 105/205', 110,916 sq ft interior fit-out of an existing facility, est. $136M, 1502 Ferris Rd. TDLR TABS
Jun 17, 2025 Building registration (TDLR) TDLR TABS: 'QTS DFW2-DC4', 413,726 sq ft two-story office and data hall shell, est. $175M, 794 W Beltline Rd; owner QTS Dallas I, LLC. TDLR TABS
Jun 17, 2025 Building registration (TDLR) TDLR TABS: 'DA11-4', 95,490 sq ft buildout inside an existing 4-story data center, est. $108.45M, 1990 N Stemmons Fwy, Dallas. TDLR TABS
Apr 10, 2025 Building registration (TDLR) TDLR TABS: 'QTS DFW2 DC2' (~470,000 sq ft, est. $300M) and DC3 (~560,000 sq ft, $350M), 303 Mason Rd, Wilmer; owner QTS Dallas I, LLC. TDLR TABS
Mar 11, 2025 Building registration (TDLR) TDLR TABS: 'AREP Powerhouse Las Colinas', 2-story 300,000 sq ft, 65 MW core and shell data center, est. $47M, 111 Customer Way, Irving. TDLR TABS
Mar 6, 2025 Building registration (TDLR) TDLR TABS: 'Digital Garland Campus' DFW40, six 8 MW suites (48 MW), 280,000 sq ft, est. $75M, 1512 Ferris Rd, Garland. TDLR TABS
Jan 30, 2025 Building registration (TDLR) TDLR TABS: 'STACK - DFW02A', 360,028 sq ft data center building, est. $79.7M, 1000 E Beltline Rd, Lancaster; owner SI DFW02A, LLC. TDLR TABS
Jan 27, 2025 Building registration (TDLR) TDLR TABS: 'Skybox - Lancaster 1 Initial Improvements', interior build-out of a 270,900 sq ft data center shell, est. $214.3M, Lancaster. TDLR TABS

What's next

These dates come from the tracker.

  • Oct. 27, 2026: Coppell City Council agenda includes an ordinance to require special use permits for data centers and crypto mining in Light Industrial zoning (Coppell agenda).
  • Statewide permit pause: Under the Governor's Sept. 21 order halting permits sought by data centers (Governor's office), TCEQ sent its Oct. 19 compliance letter: it says permits for infrastructure directly supporting data centers are paused, pending applications are being screened, and claimed authorizations are suspended where possible (TCEQ letter). The Texas Tribune reported Oct. 20 that TCEQ says stormwater permits flagged by Public Citizen were suspended (Texas Tribune). On Oct. 21 TCEQ posted that its STEERS e-filing system for automatic authorizations is temporarily shut down so staff can check whether applications relate to data centers (TCEQ STEERS notice); the Texas Tribune reports a spokesman said applications must be physically provided (Texas Tribune, Oct. 21). The tracker doesn't show whether any project in Dallas County has a pending TCEQ permit.
  • Mar. 1, 2027: Scheduled completion of DFW02A (TDLR).
  • Mar. 1, 2028: Scheduled completion of DFW02A-P2 (TDLR).
  • Dec. 14, 2028: Scheduled completion of DFW02B (TDLR).

Frequently asked questions

What data center projects are tracked in Dallas County, Texas? 11: STACK DFW02 Lancaster data center campus (DFW02A, DFW02A-P2, DFW02B) in Lancaster, listed as registered (TDLR); Schlachter hyperscale data center, Wilmer (TCEQ 'Project Longhorn') in Wilmer (area bounded by Belt Line Rd, Mason Rd, Ferris Rd and Lavender/Van Rd), listed as proposed (TCEQ air permit pending); QTS DFW2 campus (DC2–DC7), Wilmer/Lancaster in Wilmer and Lancaster (Mason Rd, W Beltline Rd, Sunrise Rd, per TDLR), listed as registered (TDLR); Stream Data Centers Wilmer (DFWC1 and Project Fir) in Wilmer (930 N Sunrise Rd and 300 S Sunrise Rd, per TDLR), listed as registered (TDLR); Digital Realty Garland campus (DFW37, DFW39, DFW40, DFW45) in Garland (Ferris Road and Holford Road, per TDLR), listed as existing campus; new buildings and fit-outs registered (TDLR); DA12 data center (1550 W Mockingbird Lane) in Dallas (1550 West Mockingbird Lane, per TDLR), listed as registered (TDLR); DA11 data center buildout (1990 N Stemmons Fwy) in Dallas (1990 N Stemmons Fwy, per TDLR), listed as existing building; buildout registered (TDLR); CoreSite DA1 (Irving) in Irving (2701 E. Grauwyler, per TDLR), listed as registered (TDLR); Edged Dallas DFW1-2 (Irving) in Irving (501 N. Wildwood Dr, per TDLR), listed as registered (TDLR); Skybox Lancaster 1 in Lancaster (2401 South Dallas Ave., per TDLR), listed as registered (TDLR); AREP Powerhouse Las Colinas in Irving (111 Customer Way, per TDLR), listed as registered (TDLR).

Who is building the Lancaster data center? Two TDLR filings are titled "STACK - DFW02A" and "STACK - DFW02A-P2" (TDLR). The newest filing (DFW02B) lists owner SI DFW02CAMPUS LLC and doesn't name STACK, but it shares the same owner address and contact (TDLR), and STACK's brochure labels a "DFW02B" building on its Lancaster campus (STACK brochure). No official record names the LLC as STACK.

How much will the STACK DFW02 buildings cost? TDLR estimates are $79.7M for DFW02A, $202.2M for DFW02A-P2 and $540M for DFW02B (TDLR A; TDLR A-P2; TDLR B).

How much power is planned at STACK's Lancaster campus? STACK's brochure cites 312 MW of critical capacity, expandable to 504 MW, on 193 acres (STACK brochure). That is a company figure; TDLR filings don't list capacity.


Get alerts for Dallas County

  • Free: Add Dallas County to your free Community weekly digest (1 county).
  • $4/mo or $36/yr: Neighbor sends same-day alerts when new Dallas County agenda items, TCEQ filings, or abatement applications appear. It also includes comment-deadline reminders. It's free on request if cost is a barrier.

Free Friday digest: Get alerts for this county (one county, free for your first month). Same-day alerts from $4/mo on Pricing.

Texas Data Center Watch is independent. No paid placement, and paying subscribers never change what this page says. See an error or a missing project? Tell us at [email protected].

Free

Get the free weekly digest for your county

Free weekly email every Friday for your first month, for 1 county you pick: new commissioners court actions, permits, filings and hearings, plus the week's top Texas changes. Every item links to its public source.

Same-day alerts come with Neighbor ($4/mo).