Live tracker: projects and dated records for Bastrop County. This page is the long-form guide.

Data Center Projects in Bastrop County, Texas

Last verified: October 27, 2026 · 3 tracked projects · 21 tracked records

Overview

Texas Data Center Watch tracks three data center projects near Cedar Creek: Pacifico Energy's 2,842-acre campus, listed as proposed, with TCEQ permits pending or challenged (Community Impact); the EdgeConneX Cedar Creek campuses, as Community Impact identifies them; and Project Longhorn – Building One. The last two are listed as registered (TDLR).

On July 20, 2026, residents filed motions asking TCEQ to overturn two construction stormwater permits for the BCG Cedar Creek Campus (Community Impact).

County action: on Aug. 10, commissioners again tabled a resolution asking the Legislature for expanded county powers over large industrial projects (Community Impact). It was on the Aug. 24 agenda as item D.8 (agenda). A related resolution about a Chapter 231 bill appeared on the Sept. 14 (agenda) and Sept. 28 (agenda) agendas. Texas Data Center Watch has not confirmed the outcome of any of these agenda items in an official record.

In September, TCEQ's air permits director told residents the Pacifico project is on hold under the Governor's permit pause (San Antonio Current).

Oct. 13 vote (E.6): Commissioners Court approved a resolution asking TCEQ to hold a public meeting on Pacifico CCK Energy LLC's electric generating unit standard permit registration 185019 (project 413471). TCEQ is not required to hold one (CBS Austin; agenda; draft resolution). Official minutes hadn't been posted as of this update.

EdgeConneX Cedar Creek (EDCAUS): Texas Data Center Watch has opened eight TDLR data center filings on FM 535:

  • EDCAUS11 and 12 (6682 FM 535): scope 729,537 sq ft each (square-footage field 730,000), est. $700M each; registered May 26, 2026; completion Dec. 31, 2028 (TDLR 11; TDLR 12).
  • EDCAUS13 and 14 (6682 FM 535): same size and cost; registered Aug. 20, 2026; start Sept. 1, 2026, completion Mar. 31, 2029 (TDLR 13; TDLR 14).
  • EDCAUS15 and 16 (6402 FM 535): 591,400 sq ft each, est. $600M each; registered Sept. 11 and 14, 2026; completion May 15, 2028 (TDLR 15; TDLR 16).
  • EDCAUS31 and 32 (6543 FM 535): scope 576,777 sq ft each (field 577,000), est. $700M each; registered Aug. 21 and 24, 2026; completions Dec. 29 and Dec. 25, 2028 (TDLR 31; TDLR 32).

None of the eight TDLR filings names EdgeConneX. They list owners Burr Computer Environment Inc (EDCAUS11–16) and Uppingham Adams Holdings, LLC (EDCAUS31–32), with the tenant shown as "Not Assigned." The EdgeConneX link comes from Community Impact, which cites the Texas Comptroller's data center registry as listing EdgeConnex MCN Austin Property 5 LLC as owner of ECX AUS11-16. Community Impact reports nine filings across three campuses totaling about 5.83 million sq ft and $5.84B, and describes the six buildings at 6682 and 6402 FM 535 as Campus No. 2, under construction per a photo caption (Community Impact).

Project Longhorn – Building One on Earl Callahan Rd near Walter Hoffman Road: an Oct. 7, 2026 TDLR registration lists a 498,165 sq ft data center building at an estimated $366M, with a Nov. 30, 2026 start and a Jan. 31, 2028 completion. The owner is listed as Roger Donald Wallace of Austin, and the design firm as Gensler (Dallas); the TDLR filing names neither Pacifico nor BlackChamber (TDLR). Community Impact (Oct. 8) identifies the filing as the first of two data center buildings planned by Pacifico Energy and BlackChamber on the 2,842-acre Cedar Creek property, with BlackChamber developing the data center and Pacifico the power facility (Community Impact).

Note: "registered" means a state accessibility (TDLR) building registration, not an environmental permit or local approval.

Tracked projects

Project Developer Status Capacity / size Investment Key dates Sources
Cedar Creek Pacifico campus (see also edgeconnex-cedarcreek), Cedar Creek Pacifico Energy Proposed (TCEQ permits pending/challenged) Pacifico campus 2,842 acres Not recorded Jul 20 2026 residents filed motions to overturn two TCEQ construction stormwater permits for BCG Cedar Creek Campus (Community Impact) · Aug 10 2026 resolution asking Legislature for expanded county powers tabled again (Community Impact) · Aug 24 2026 resolution on agenda (item D.8 · outcome not confirmed in an official record) · Sep 14 and Sep 28 2026 agendas list a Chapter 231 bill resolution (outcome not confirmed) · Sep 2026 TCEQ air permits director told residents Pacifico project is on hold under Governor's pause (per SA Current) · Oct 13 2026 Commissioners Court agenda item E.6: resolution requesting TCEQ hold a public meeting on Pacifico CCK Energy LLC Electric Generating Unit Standard Permit registration 185019 / Project 413471 (official agenda/AIR-26-745) · Oct 13 2026 court approved the resolution (CBS Austin · minutes not yet posted as of Oct 15 2026) Community Impact · Bastrop County agenda 1 · San Antonio Current · CBS Austin · Bastrop County agenda 2
EdgeConneX Cedar Creek campuses (EDCAUS), Cedar Creek EdgeConneX (per Community Impact, citing Texas Comptroller data center registry for ECX AUS11-16 / EdgeConnex MCN Austin Property 5 LLC); TDLR owners Burr Computer Environment Inc (EDCAUS11, 12, 13, 14, 15, 16) and Uppingham Adams Holdings, LLC (EDCAUS31, 32) Registered (TDLR); under construction (Campus No. 2 per Community Impact photo caption) Verified TDLR filings opened: EDCAUS11, EDCAUS12, EDCAUS13 and EDCAUS14 at 6682 FM 535, each scope 729,537 sq ft / square-footage field 730,000, est. $700M each (TDLR; 13 and 14 registered Aug 20 2026); EDCAUS15 and EDCAUS16 at 6402 FM 535, 591,400 sq ft, est. $600M each (TDLR); EDCAUS31 and EDCAUS32 at 6543 FM 535, each scope 576,777 sq ft / square-footage field 577,000, est. $700M each (TDLR; 31 registered Aug 21 2026). Community Impact (Oct 7 2026, news) reports nine TDLR data-center filings across three Cedar Creek campuses totaling about 5.83M sq ft and $5.84B; eight of those TABS pages are now opened. None of the eight opened TDLR filings names EdgeConneX: owners are Burr Computer Environment Inc (Houston) and Uppingham Adams Holdings, LLC (Wilmington, DE), tenant Not Assigned (TDLR, rechecked Oct 13 2026). The EdgeConneX link rests on Community Impact (news) citing the Comptroller registry, which has not been opened here Est. costs as filed on opened TDLR records: $700M (EDCAUS11, 12, 13, 14, 31, 32); $600M (EDCAUS15, 16). Community Impact: $5.84B across nine buildings (news) May 26 2026 EDCAUS11 and EDCAUS12 registered (start Jun 30 2026, completion Dec 31 2028 · Project Registered) (TDLR) · Aug 20 2026 EDCAUS13 and EDCAUS14 registered (start Sep 1 2026, completion Mar 31 2029 · Project Registered · owner Burr Computer Environment Inc) (TDLR) · Aug 21 2026 EDCAUS31 registered (start Oct 5 2026, completion Dec 29 2028 · Project Registered · owner Uppingham Adams Holdings, LLC) (TDLR) · Aug 24 2026 EDCAUS32 registered (start Oct 5 2026, completion Dec 25 2028 · Project Registered) (TDLR) · Sep 11 2026 EDCAUS15 and Sep 14 2026 EDCAUS16 registered (start Nov 2 2026, completion May 15 2028 · Project Registered) (TDLR) · Community Impact (Oct 7 2026): Campus No. 2 is the six buildings at 6682 and 6402 FM 535 · Comptroller registry lists EdgeConnex MCN Austin Property 5 LLC as owner and EdgeConnex MCN Austin Operations 5 LLC as occupant/operator for ECX AUS11-16 (news). Separate from Pacifico Cedar Creek campus (bastrop-cedarcreek) and from Project Longhorn Building One (longhorn-cedarcreek) · Jul 14 2025 'ECX AUSTIN DFW33220N' (facility AUS02) registered at 8001 Wolf Ln Bldg 2 / 6752 FM 535, Cedar Creek (new 2-story data center, 578,000 sq ft, est. $440M · owner DFW33220N, LLC, the same entity named in the Aqua WSC agreement for the EdgeConneX Austin development · start Aug 1 2025, completion Jun 14 2026 · Review Complete) (TDLR, found Oct 18 2026) TDLR TABS 1 · TDLR TABS 2 · TDLR TABS 3 · TDLR TABS 4 · TDLR TABS 5 · TDLR TABS 6 · TDLR TABS 7 · TDLR TABS 8 · Community Impact · TDLR TABS 9
Project Longhorn – Building One, Cedar Creek (Earl Callahan Rd near Walter Hoffman Road) Owner Roger Donald Wallace (TDLR; tenant field 'Not Assigned'); BlackChamber developing the data center portion, Pacifico Energy the power facility (Community Impact, news); design firm Gensler (Dallas) Registered (TDLR) 498,165 sq ft (TDLR) Est. $366M (TDLR) Oct 7 2026 TDLR registration TABS2027002962 for Project Longhorn – Building One (Project Registered · New Construction · Type II-B Construction Data Center (S-1) PEMB with Business accessory use · start Nov 30 2026, completion Jan 31 2028 · address Earl Callahan Rd near Walter Hoffman Road, Cedar Creek 78612, Bastrop County · owner Roger Donald Wallace, 9505 Johnny Morris Road, Austin · design Gensler Dallas) (TDLR). Oct 8 2026 Community Impact identifies the filing as the first of two data center buildings planned by Pacifico Energy and BlackChamber on the 2,842-acre Cedar Creek property · the TDLR record itself names neither company (news · TDLR). Separate EdgeConneX Cedar Creek campuses (edgeconnex-cedarcreek) · related to Pacifico Cedar Creek (bastrop-cedarcreek) per Community Impact TDLR TABS

Recorded benefits and concerns (Cedar Creek Pacifico campus (see also edgeconnex-cedarcreek)):

  • Concerns: Air permits (minor vs. major permit dispute); limited county authority

Sources for each project are linked in the table. Figures labeled "company" come from the developer.

Record timeline

Date Type What happened Source
Oct 29, 2026 City council City of Bastrop notice: Data Center Town Hall Oct 29, 5:30 p.m., Bastrop Convention Center, 1408 Chestnut St; no council action. City of Bastrop notice
Oct 13, 2026 Commissioners court Agenda item E.6: resolution asking TCEQ for public meeting on Pacifico CCK Energy EGU standard permit 185019 / 413471. Bastrop County agenda
Oct 13, 2026 Commissioners court AIR-26-745 draft resolution text: requests TCEQ public meeting on Pacifico CCK registration 185019 / project 413471. Bastrop County agenda
Oct 13, 2026 Commissioners court Court approved resolution asking TCEQ for a public meeting on Pacifico's Cedar Creek gas plant air permit; TCEQ not required to hold one (CBS Austin; minutes not yet posted). CBS Austin
Oct 9, 2026 News DCD: Project Longhorn targets Nov 30 2026 construction start; full build 710 MW gas-turbine power for 490 MW IT; Anthropic reportedly in lease talks. DCD
Oct 8, 2026 News Community Impact: Project Longhorn filing is first of two Pacifico–BlackChamber data center buildings; BlackChamber develops the data center, Pacifico the power plant. Community Impact
Oct 7, 2026 News Community Impact: EdgeConneX Cedar Creek TDLR filings reach about $5.84B across nine buildings / three campuses; cites Comptroller registry for ECX AUS11-16. Community Impact
Oct 7, 2026 Building registration (TDLR) TDLR TABS: Project Longhorn Building One, 498,165 sq ft, est. $366M, Earl Callahan Rd, Cedar Creek; owner Roger Donald Wallace. TDLR TABS
Sep 28, 2026 Commissioners court Agenda item D.6 (AIR-26-705): resolution regarding a Chapter 231 bill to protect sensitive and rural areas of Bastrop County. Outcome not confirmed. Bastrop County agenda
Sep 14, 2026 Commissioners court Agenda item (AIR-26-670): resolution regarding a Chapter 231 bill to protect sensitive and rural areas of Bastrop County. Outcome not confirmed. Bastrop County agenda
Sep 14, 2026 Building registration (TDLR) TDLR TABS: EDCAUS16, 591,400 sq ft, est. $600M, 6402 FM 535, Cedar Creek; owner Burr Computer Environment Inc. TDLR TABS
Sep 11, 2026 Building registration (TDLR) TDLR TABS: EDCAUS15, 591,400 sq ft, est. $600M, 6402 FM 535, Cedar Creek; owner Burr Computer Environment Inc; start Nov 2 2026. TDLR TABS
Aug 24, 2026 Commissioners court On agenda (item D.8, AIR-26-591): resolution petitioning Legislature for expanded county regulatory powers over large industrial projects. Outcome not confirmed in official record. Bastrop County agenda
Aug 24, 2026 Building registration (TDLR) TDLR TABS: EDCAUS32, ~577,000 sq ft, est. $700M, 6543 FM 535, Cedar Creek; owner Uppingham Adams Holdings, LLC. TDLR TABS
Aug 21, 2026 Building registration (TDLR) TDLR TABS: EDCAUS31, ~577,000 sq ft, est. $700M, 6543 FM 535, Cedar Creek; owner Uppingham Adams Holdings, LLC. TDLR TABS
Aug 20, 2026 Building registration (TDLR) TDLR TABS: EDCAUS13, ~730,000 sq ft, est. $700M, 6682 FM 535, Cedar Creek; owner Burr Computer Environment Inc. TDLR TABS
Aug 20, 2026 Building registration (TDLR) TDLR TABS: EDCAUS14, ~730,000 sq ft, est. $700M, 6682 FM 535, Cedar Creek; owner Burr Computer Environment Inc. TDLR TABS
Aug 10, 2026 Commissioners court Commissioners tabled again a resolution asking the Legislature for expanded county powers over large industrial projects (Community Impact). Community Impact
May 26, 2026 Building registration (TDLR) TDLR TABS: EDCAUS11, ~730,000 sq ft, est. $700M, 6682 FM 535, Cedar Creek; owner Burr Computer Environment Inc. TDLR TABS
May 26, 2026 Building registration (TDLR) TDLR TABS: EDCAUS12, ~730,000 sq ft, est. $700M, 6682 FM 535, Cedar Creek; owner Burr Computer Environment Inc. TDLR TABS
Jul 14, 2025 Building registration (TDLR) TDLR TABS: 'ECX AUSTIN DFW33220N' (AUS02), new 2-story 578,000 sq ft data center, est. $440M, 6752 FM 535; owner DFW33220N, LLC. TDLR TABS

What's next

These dates come from the tracker. Texas Data Center Watch has no recorded upcoming Bastrop County Commissioners Court votes on data centers; the Oct. 29 item is a City of Bastrop town hall.

  • Oct. 29, 2026, 5:30 p.m.: City of Bastrop Data Center Town Hall at the Bastrop Convention Center, 1408 Chestnut St.; the city notice lists no council action (City of Bastrop notice).
  • Statewide permit pause: Under the Governor's Sept. 21 order halting permits sought by data centers (Governor's office), TCEQ sent its Oct. 19 compliance letter: it says permits for infrastructure directly supporting data centers are paused, pending applications are being screened, and claimed authorizations are suspended where possible (TCEQ letter). The Texas Tribune reported Oct. 20 that TCEQ says stormwater permits flagged by Public Citizen were suspended (Texas Tribune). On Oct. 21 TCEQ posted that its STEERS e-filing system for automatic authorizations is temporarily shut down so staff can check whether applications relate to data centers (TCEQ STEERS notice); the Texas Tribune reports a spokesman said applications must be physically provided (Texas Tribune, Oct. 21). Per the San Antonio Current, TCEQ told residents the Pacifico project is on hold under the pause.
  • Jan. 31, 2028: Scheduled completion of Project Longhorn – Building One (TDLR).
  • May 15, 2028 to Mar. 31, 2029: Scheduled completions of the EDCAUS buildings, per their TDLR registrations (TDLR 15; TDLR 13).

Frequently asked questions

What data center projects are tracked in Bastrop County, Texas? Three: Cedar Creek Pacifico campus (see also edgeconnex-cedarcreek) in Cedar Creek, listed as proposed (TCEQ permits pending/challenged); EdgeConneX Cedar Creek campuses (EDCAUS) in Cedar Creek, listed as registered (TDLR); under construction (Campus No. 2 per Community Impact photo caption); Project Longhorn – Building One in Cedar Creek (Earl Callahan Rd near Walter Hoffman Road), listed as registered (TDLR).

Did Bastrop County pass a resolution asking for more authority over data centers? Not confirmed. Commissioners tabled it again on Aug. 10 (Community Impact), and it was on the Aug. 24 agenda (agenda). A related Chapter 231 resolution appeared on the Sept. 14 and Sept. 28 agendas. Texas Data Center Watch has not confirmed any outcome in an official record.

Is the Pacifico project in Cedar Creek on hold? According to the San Antonio Current, TCEQ's air permits director told residents in September that the Pacifico project is on hold under the Governor's permit pause.

What are residents challenging? On July 20, 2026, residents filed motions asking TCEQ to overturn two construction stormwater permits for the BCG Cedar Creek Campus (Community Impact). The tracker also records a dispute over whether air permits should be minor or major.

Is EdgeConneX building in Cedar Creek? Community Impact reports that it is, citing the Comptroller's data center registry (Community Impact). The eight TDLR filings Texas Data Center Watch opened don't name EdgeConneX; they list owners Burr Computer Environment Inc and Uppingham Adams Holdings, LLC, with no tenant assigned (TDLR).

How big are the Cedar Creek filings? The eight EDCAUS filings are estimated at $600M–$700M per building (TDLR). Community Impact puts the total at about $5.84B across nine buildings (Community Impact). Project Longhorn Building One is a separate $366M filing (TDLR).

Did Bastrop County ask TCEQ for a public meeting on Pacifico's air permit? Yes. On Oct. 13, 2026, Commissioners Court approved a resolution asking TCEQ for a public meeting on Pacifico CCK registration 185019; TCEQ is not required to hold one (CBS Austin).

Who is behind Project Longhorn? TDLR lists owner Roger Donald Wallace and design firm Gensler; it doesn't name a data center company (TDLR). Community Impact identifies it as a Pacifico–BlackChamber building (Community Impact).


Get alerts for Bastrop County

  • Free: Add Bastrop County to your free Community weekly digest (1 county).
  • $4/mo or $36/yr: Neighbor sends same-day alerts when new Bastrop County agenda items, TCEQ filings, or abatement applications appear. It also includes comment-deadline reminders. It's free on request if cost is a barrier.

Free Friday digest: Get alerts for this county (one county, free for your first month). Same-day alerts from $4/mo on Pricing.

Texas Data Center Watch is independent. No paid placement, and paying subscribers never change what this page says. See an error or a missing project? Tell us at [email protected].