Home / Dallas County / Project
Stream Data Centers Wilmer (DFWC1 and Project Fir)
Stream Data Centers (TDLR owners SDC DFWC, LP and SDC DFW VIII, L.P.)
- Status
- Registered (TDLR)
- Developer / parties
- Stream Data Centers (TDLR owners SDC DFWC, LP and SDC DFW VIII, L.P.)
- Location
- Wilmer (930 N Sunrise Rd and 300 S Sunrise Rd, per TDLR), Dallas County
- Size
- DFWC1: new 2-story 48 MW, 360,750 sq ft data center, substation and campus entrance; Project Fir: 85,625 sq ft data center core and shell next to an existing data center (TDLR)
- Investment
- DFWC1 est. $300M; Project Fir est. $167.3M (TDLR, as filed)
- Last verified
- 2026-10-18
Milestones
- Sep 21 2025 'Stream Data Centers - DFWC1' registered (start Apr 1 2026, completion Oct 27 2027; Review Complete)
- Oct 22 2025 'Project Fir' (Stream Wilmer FIR) registered as an addition next to an existing data center (completion Dec 1 2027; Project Registered) (TDLR)
Linked power & water
Power
- Official record DFWC1 substation: The DFWC1 TDLR filing includes a new 2-story 48 MW data center building, a substation and a campus entrance (TDLR). tdlr.texas.gov ↗
Related records
2025-10-22
Building registration (TDLR) Official record
TDLR TABS: 'Project Fir', 85,625 sq ft data center core and shell next to an existing data center, est. $167.3M, 300 S Sunrise Rd, Wilmer.
Source: tdlr.texas.gov ↗2025-09-21
Building registration (TDLR) Official record
TDLR TABS: 'Stream Data Centers - DFWC1', new 2-story 48 MW 360,750 sq ft data center plus substation, est. $300M, 930 N Sunrise Rd, Wilmer.
Source: tdlr.texas.gov ↗Sources
- Official record tdlr.texas.gov
- Official record tdlr.texas.gov
Free
Get the free weekly digest for your county
Free weekly email every Friday for your first month, for 1 county you pick: new commissioners court actions, permits, filings and hearings, plus the week's top Texas changes. Every item links to its public source.
Same-day alerts come with Neighbor ($4/mo).