Home / Stonewall County / Project
Crusoe Stonewall County data center complex
Crusoe Energy Systems LLC
- Status
- Proposed / in development
- Developer / parties
- Crusoe Energy Systems LLC
- Location
- Aspermont area; near the Flat Top and Greater Swenson ranch parcels (Double Mountain Chronicle), Stonewall County
- Size
- About 1,300 acres in the proposed reinvestment zone, within a project area previously described as about 3,200 acres (Double Mountain Chronicle, citing earlier project materials). No MW figure in any record opened
- Reported benefits
- Company application projected at least 80 permanent jobs at $100,000+ plus benefits, ~$8M annual payroll after full buildout, and up to 5,000 peak construction workers (application figures via Double Mountain Chronicle; not guaranteed). Application proposed a PILOT equal to 15% of real-property improvement taxes during the abatement (per Double Mountain Chronicle; county called it a starting point)
- Concerns / impacts
- Neighboring landowner raised noise, lighting, heat, water use and construction concerns; public questions on water, jobs, infrastructure, school district boundaries (Double Mountain Chronicle)
- Last verified
- 2026-10-14
Milestones
- Late Mar 2026 Crusoe tax abatement application discussed by Commissioners Court (Double Mountain Chronicle, Apr 9 2026)
- commissioners later approved a reinvestment zone (Double Mountain Chronicle; order not opened)
- Jun 16 2026 county cancelled the Jun 22 abatement hearing citing ongoing negotiations with Crusoe Energy Systems LLC for a Data Center Complex (official notice)
- Aug 2026 notice set a Sep 28 public hearing on intent to enter a tax abatement agreement with Crusoe (official)
- Sep 22 2026 county cancelled the Sep 28 hearing, again citing ongoing negotiations (official notice)
- no new hearing date posted as of Oct 14 2026. Double Mountain Chronicle (Oct 8 2026) reports the county is waiting on state data center reviews that could extend into December
Linked power & water
Power
- News report Possible natural gas generation facility (discussed, not filed): Crusoe's proposed campus 'has included discussion of a possible natural gas generation facility' (Double Mountain Chronicle, May 7 2026). No TCEQ air permit application found on the pending list Oct 18 2026. doublemountainchronicle.com ↗
Related records
Double Mountain Chronicle: second hearing cancelled as county waits for state data center reviews that could extend into December.
Source: doublemountainchronicle.com ↗Double Mountain Chronicle: Sep 28 abatement hearing cancelled; reinvestment zone approved earlier (~1,300 acres); application projected 80+ jobs at $100K+ (company figures).
Source: doublemountainchronicle.com ↗County Judge notice cancels Sep 28 Crusoe tax abatement hearing, citing ongoing negotiations; no new date given.
Source: stonewallcounty.org ↗Meeting notice: Sep 28 public hearing on Stonewall County's intent to enter into a Tax Abatement Agreement with Crusoe Energy Systems, LLC.
Source: stonewallcounty.org ↗County Judge notice cancels Jun 22 public hearing due to ongoing tax abatement negotiations with Crusoe Energy Systems LLC for a Data Center Complex.
Source: stonewallcounty.org ↗Double Mountain Chronicle: Crusoe filed a tax abatement application for a data center campus on about 3,200 acres near Flat Top and Greater Swenson parcels.
Source: doublemountainchronicle.com ↗Sources
- News report stonewallcounty.org
- News report stonewallcounty.org
- News report stonewallcounty.org
- News report doublemountainchronicle.com
- News report doublemountainchronicle.com
- News report doublemountainchronicle.com