Home / Austin County / Project

CleanSpark Austin County AI data center campus (Substation Road, Sealy area)

CleanSpark, Inc. (subsidiary CleanSpark Data I, LLC; seller Priority Power Management, per SEC 10-Q)

Status
Proposed / in development (county moratorium in effect)
Developer / parties
CleanSpark, Inc. (subsidiary CleanSpark Data I, LLC; seller Priority Power Management, per SEC 10-Q)
Location
Off Substation Road (per Banner Press); Sealy area, Austin County
Size
~271 acres; long-term power supply agreements totaling 285 MW; energization of more than 200 MW expected 1H 2027 (company claim)
Investment
Land/power rights: $65.698M total (cash, 1,788,834 shares and deferred consideration) + $15.087M adjacent land Apr 17 2026 (SEC 10-Q, company filing)
Concerns / impacts
County moratorium pending a health-and-safety review (official order)
Last verified
2026-10-27

Milestones

Figures are attributed in parentheses to the outlet or company that reported them. Where sources disagree, we show both.

  1. Oct 27 2025 CleanSpark Data I, LLC agreed to buy real estate and a land purchase option in Austin County from Priority Power Management
  2. Apr 17 2026 bought adjacent land for $15.087M (SEC 10-Q, company filing)
  3. Oct 29 2025 CleanSpark announced rights to ~271 acres and 285 MW
  4. substation construction plan underway (company)
  5. Jul 27 2026 Austin County Commissioners Court unanimously adopted a moratorium on BESS and data center construction in unincorporated areas
  6. CleanSpark's CEO spoke at the session
  7. moratorium not targeted at CleanSpark (Banner Press, news; executed order on county site, official)
  8. CleanSpark's 10-Q cites the Austin County moratorium as a risk (company filing)

Linked power & water

Power

  • Company claim 285 MW power supply agreements; substation construction underway: CleanSpark says it executed long-term power supply agreements totaling 285 MW and a substation construction plan is underway; it is evaluating nearby gas pipelines for behind-the-meter generation. investors.cleanspark.com ↗

Power and water projects tied to this data center: on-site or dedicated generation, utility and grid capacity deals, substations, water supply, reclaimed water and wastewater permits. Each item is labeled by source type.

Related records

2026-08-05
News News report Austin County · CleanSpark Austin County AI data center campus (Substation Road, Sealy area)

Banner Press: court voted unanimously Jul 27 for the moratorium; CleanSpark wants a data center off Substation Road.

Source: bannerpresspaper.com ↗
2026-06-30
Federal filing Official record Austin County · CleanSpark Austin County AI data center campus (Substation Road, Sealy area)

CleanSpark 10-Q: Austin County land/option bought from Priority Power for $65.7M; adjacent land Apr 17 ($15.1M) (company filing).

Source: sec.gov ↗
2025-10-29
Company announcement News report Austin County · CleanSpark Austin County AI data center campus (Substation Road, Sealy area)

CleanSpark: rights to ~271 acres in Austin County and 285 MW of power supply agreements for an AI data center campus (company claim).

Source: investors.cleanspark.com ↗

Sources

Found an error? Email [email protected] with a source link.