Amp Z Champion Data Center (Project LufKin / former Southland Paper Mill)
Amp Z Champion Data Center Holdings LLC (Amp Energy affiliate per DCD); site option from Verdant Industries entities (per Lufkin Daily News citing county property records)
- Status
- Proposed / in development
- Developer / parties
- Amp Z Champion Data Center Holdings LLC (Amp Energy affiliate per DCD); site option from Verdant Industries entities (per Lufkin Daily News citing county property records)
- Location
- Lufkin area (east of city, US Hwy 103 / former Southland–Abitibi mill), Angelina County
- Size
- About 1,041 acres under purchase option at the former Southland Paper Mill (Lufkin Daily News citing county property records, via DCD). Company website claims (via DCD, Feb 2026): 55 MW grid connection now, 175 MW in 2026, 1.1 GW grid by 2028, plus 1 GW self-generation by 2029 for ~2.1 GW ultimate — company figures, not county-verified
- Investment
- More than $1B projected investment (per Lufkin Daily News, Oct 10 2026, news; not a county figure)
- Reported benefits
- City of Lufkin FAQ (developer estimates relayed by city): about 30 permanent and 500 construction jobs; closed-loop cooling with estimated treated water use about 500 gallons/day after initial fill (company/city FAQ, not a permit limit)
- Concerns / impacts
- Water use is the leading public concern (Lufkin Daily News); county says it has limited regulatory authority outside city limits without an abatement (news)
- Last verified
- 2026-10-13
Milestones
- Planning phase
- not approved for construction (City of Lufkin FAQ, official, opened Oct 13 2026). Feb 2026 DCD: Amp Z option on ~1,041 acres (news). County Judge Keith Wright: 10-year property tax abatement application rejected
- developer had not submitted another as of Oct 10 2026 (Lufkin Daily News, news). Oct 13 2026 Angelina County Commissioners Court agenda item: discussion/action on proposal for legal research and drafting of a road-use agreement between Angelina County and AMP Z Champion Data Center Holdings LLC, fees from Legal Services (official agenda COM-AGEN101326.pdf). Meeting 10 a.m.
- outcome not posted as of Oct 13 2026 (latest minutes on county site are Sep 8 2026). No official record of the abatement rejection found: Jun 9 2026 minutes record only discussion and public comment, Aug 25 2026 minutes record retaining Allison, Bass and Magee LLP for Ch. 312 work (minutes, official)
- the rejection rests on Judge Wright's statement to the Lufkin Daily News (news)
Linked power & water
Power
- News report Grid capacity plus 1 GW self-generation: Company claims 175 MW grid-connected in 2026 rising to 1.1 GW by 2028, plus 1 GW of self-generation by 2029 (DCD). datacenterdynamics.com ↗
Related records
Agenda: authorize legal research and drafting of road-use agreement with AMP Z Champion Data Center Holdings LLC.
Source: angelinacounty.net ↗the936.com: Oct 13 court to consider authorizing legal work on Amp Z road-use agreement; not approval of a finished deal.
Source: the936.com ↗Lufkin Daily News: county rejected Amp Z 10-year tax abatement; Judge Wright seeks clearer project and water estimates.
Source: lufkindailynews.com ↗DCD: Amp Z option on ~1,041-acre former Southland mill; company site claims ramp to ~2.1 GW with on-site generation.
Source: datacenterdynamics.com ↗Sources
- News report angelinacounty.net
- News report cityoflufkin.com
- News report the936.com
- News report lufkindailynews.com
- News report datacenterdynamics.com