Amp Z Champion Data Center (Project LufKin / former Southland Paper Mill)

Amp Z Champion Data Center Holdings LLC (Amp Energy affiliate per DCD); site option from Verdant Industries entities (per Lufkin Daily News citing county property records)

Status
Proposed / in development
Developer / parties
Amp Z Champion Data Center Holdings LLC (Amp Energy affiliate per DCD); site option from Verdant Industries entities (per Lufkin Daily News citing county property records)
Location
Lufkin area (east of city, US Hwy 103 / former Southland–Abitibi mill), Angelina County
Size
About 1,041 acres under purchase option at the former Southland Paper Mill (Lufkin Daily News citing county property records, via DCD). Company website claims (via DCD, Feb 2026): 55 MW grid connection now, 175 MW in 2026, 1.1 GW grid by 2028, plus 1 GW self-generation by 2029 for ~2.1 GW ultimate — company figures, not county-verified
Investment
More than $1B projected investment (per Lufkin Daily News, Oct 10 2026, news; not a county figure)
Reported benefits
City of Lufkin FAQ (developer estimates relayed by city): about 30 permanent and 500 construction jobs; closed-loop cooling with estimated treated water use about 500 gallons/day after initial fill (company/city FAQ, not a permit limit)
Concerns / impacts
Water use is the leading public concern (Lufkin Daily News); county says it has limited regulatory authority outside city limits without an abatement (news)
Last verified
2026-10-13

Milestones

Figures are attributed in parentheses to the outlet or company that reported them. Where sources disagree, we show both.

  1. Planning phase
  2. not approved for construction (City of Lufkin FAQ, official, opened Oct 13 2026). Feb 2026 DCD: Amp Z option on ~1,041 acres (news). County Judge Keith Wright: 10-year property tax abatement application rejected
  3. developer had not submitted another as of Oct 10 2026 (Lufkin Daily News, news). Oct 13 2026 Angelina County Commissioners Court agenda item: discussion/action on proposal for legal research and drafting of a road-use agreement between Angelina County and AMP Z Champion Data Center Holdings LLC, fees from Legal Services (official agenda COM-AGEN101326.pdf). Meeting 10 a.m.
  4. outcome not posted as of Oct 13 2026 (latest minutes on county site are Sep 8 2026). No official record of the abatement rejection found: Jun 9 2026 minutes record only discussion and public comment, Aug 25 2026 minutes record retaining Allison, Bass and Magee LLP for Ch. 312 work (minutes, official)
  5. the rejection rests on Judge Wright's statement to the Lufkin Daily News (news)

Linked power & water

Power

  • News report Grid capacity plus 1 GW self-generation: Company claims 175 MW grid-connected in 2026 rising to 1.1 GW by 2028, plus 1 GW of self-generation by 2029 (DCD). datacenterdynamics.com ↗

Power and water projects tied to this data center: on-site or dedicated generation, utility and grid capacity deals, substations, water supply, reclaimed water and wastewater permits. Each item is labeled by source type.

Related records

2026-10-13
Commissioners court News report Angelina County · Amp Z Champion Data Center (Project LufKin / former Southland Paper Mill)

Agenda: authorize legal research and drafting of road-use agreement with AMP Z Champion Data Center Holdings LLC.

Source: angelinacounty.net ↗
2026-10-11
News News report Angelina County · Amp Z Champion Data Center (Project LufKin / former Southland Paper Mill)

the936.com: Oct 13 court to consider authorizing legal work on Amp Z road-use agreement; not approval of a finished deal.

Source: the936.com ↗
2026-10-10
News News report Angelina County · Amp Z Champion Data Center (Project LufKin / former Southland Paper Mill)

Lufkin Daily News: county rejected Amp Z 10-year tax abatement; Judge Wright seeks clearer project and water estimates.

Source: lufkindailynews.com ↗
2026-02-05
News News report Angelina County · Amp Z Champion Data Center (Project LufKin / former Southland Paper Mill)

DCD: Amp Z option on ~1,041-acre former Southland mill; company site claims ramp to ~2.1 GW with on-site generation.

Source: datacenterdynamics.com ↗

Sources

Found an error? Email [email protected] with a source link.