Home / Childress County / Project
IREN Childress campus (Horizon AI buildings for Microsoft)
IREN; Microsoft (customer)
- Status
- Partially operational
- Developer / parties
- IREN; Microsoft (customer)
- Location
- Childress, Childress County
- Size
- 750 MW total capacity on a 576-acre freehold site (IREN); Horizon 1–4 are four 50 MW (IT load) direct-to-chip liquid-cooled buildings for Microsoft (DCD)
- Investment
- Microsoft signed a five-year, $9.7bn cloud services contract with IREN in Nov 2025 (DCD)
- Last verified
- 2026-10-18
Milestones
- Site previously hosted cryptomining (DCD)
- Aug 2026 Horizon 1 delivered to and accepted by Microsoft
- Horizons 2–4 scheduled for delivery later in 2026 (DCD, Aug 17 2026)
Linked power & water
Power
- Company claim IREN-owned on-site substations (ERCOT): Directly connected to the ERCOT grid via on-site substations owned by IREN (IREN). iren.com ↗
Related records
Sources
- Company claim iren.com
- News report datacenterdynamics.com
Free
Get the free weekly digest for your county
Free weekly email every Friday for your first month, for 1 county you pick: new commissioners court actions, permits, filings and hearings, plus the week's top Texas changes. Every item links to its public source.
Same-day alerts come with Neighbor ($4/mo).