Abernathy AI data center campus (Fluidstack / TeraWulf joint venture)
Fluidstack (majority after Jul 2026 sale); TeraWulf (minority); Google (lease backstop, per DCD)
- Status
- In development
- Developer / parties
- Fluidstack (majority after Jul 2026 sale); TeraWulf (minority); Google (lease backstop, per DCD)
- Location
- Abernathy, Hale County, Lubbock County
- Size
- 168 MW critical IT load (TeraWulf; DCD). Site county not stated in opened sources; Abernathy lies in Hale and Lubbock counties (DCD)
- Last verified
- 2026-10-18
Milestones
- Oct 2025 TeraWulf and Fluidstack formed the joint venture, Google-backed (DCD)
- 2026 TeraWulf sold its majority interest to Fluidstack (TeraWulf)
Linked power & water
Power
- Company claim Xcel Energy / Southwestern Public Service (SPP) 345 kV interconnection: Abernathy site: 120 acres, grid SPP, utility Xcel Energy – Southwestern Public Service territory, 345 kV interconnection; power 100% passed through to the tenant (TeraWulf investor presentation filed with the SEC, Oct 2025). sec.gov ↗
Related records
Sources
- News report datacenterdynamics.com
- Company claim investors.terawulf.com
Free
Get the free weekly digest for your county
Free weekly email every Friday for your first month, for 1 county you pick: new commissioners court actions, permits, filings and hearings, plus the week's top Texas changes. Every item links to its public source.
Same-day alerts come with Neighbor ($4/mo).