Mitchell County · Colorado City (951 County Road 204)
Barber Lake data center
Cipher Digital (owner/operator); Fluidstack (tenant; Google backstops the lease, per DCD and SanAngeloLive); Anthropic (tenant, per SanAngeloLive)
Under construction
Size: 800,000 sq ft data center facility (TDLR); 300 MW (SanAngeloLive); 168 MW of IT capacity leased to Fluidstack (DCD, Nov 2025)
Investment: TDLR est. cost $50M (as filed); contracted lease revenue over $9B across 20 years (company)
Last verified 2026-10-18 · 4 sources